AACE-PSP Exam Question 41

You are retained by a contractor who asks you to perform a simple as-planned versus as-built analysis (APAB) of a large hydro-electric dam project that took more than five years to complete. Your analysis will form the basis of a change order that requests a time extension. You suggest using a different methodology for quantifying the delay. Which of the following reasons for recommending a different analysis does NOT apply to a simple APAB analysis?
  • AACE-PSP Exam Question 42

    How many work days does it take to move the product from testing to sale?
  • AACE-PSP Exam Question 43

    Crane operators require 1 hour prep and 1 hour clean-up and inspection per day. There is only 1 crane operator allocated per crane. Crane operators are not allowed to work more than 8 hours a day. Lunchtime break lasts 1 hour. Assuming a 10 minute cycle time, how many lifts per day can be expected?
  • AACE-PSP Exam Question 44

    Using the "normal" schedule, theoretically construct a hammock for activities 6001-6003. What is the duration of the hammock?