CEM Exam Question 41

A cooling tower delivers 29°C water to a central chilled water plant. The cooling tower is capable of delivering water to the chilled-water plant with a 6°C approach temperature to the ambient wet bulb temperature. Using this information, what type of control strategy would you recommend be added to the cooling tower operation to save additional energy?
  • CEM Exam Question 42

    Why do electric utility companies transmit power at high voltages?
    SELECT THE CORRECT ANSWER
  • CEM Exam Question 43

    A facility has a monthly peak power demand of 1,000 kW and an average power factor of 80%. The facility pays a demand charge of $7.50/kVA-month. What is the additional cost per month because the power factor is less than 100%?
  • CEM Exam Question 44

    At the end of a performance contract, who owns the equipment installed by the project?
  • CEM Exam Question 45

    An air-conditioning system at full load is rated at 70-kW (thermal cooling) and has a coefficient of performance (COP) of 4.1. What is the electrical load at full load?