CEM Exam Question 41
A cooling tower delivers 29°C water to a central chilled water plant. The cooling tower is capable of delivering water to the chilled-water plant with a 6°C approach temperature to the ambient wet bulb temperature. Using this information, what type of control strategy would you recommend be added to the cooling tower operation to save additional energy?
CEM Exam Question 42
Why do electric utility companies transmit power at high voltages?
SELECT THE CORRECT ANSWER
SELECT THE CORRECT ANSWER
CEM Exam Question 43
A facility has a monthly peak power demand of 1,000 kW and an average power factor of 80%. The facility pays a demand charge of $7.50/kVA-month. What is the additional cost per month because the power factor is less than 100%?
CEM Exam Question 44
At the end of a performance contract, who owns the equipment installed by the project?
CEM Exam Question 45
An air-conditioning system at full load is rated at 70-kW (thermal cooling) and has a coefficient of performance (COP) of 4.1. What is the electrical load at full load?