PSP Exam Question 31

You are retained by a contractor who asks you to perform a simple as-planned versus as-built analysis (APAB) of a large hydro-electric dam project that took more than five years to complete. Your analysis will form the basis of a change order that requests a time extension. You suggest using a different methodology for quantifying the delay. Which of the following reasons for recommending a different analysis does NOT apply to a simple APAB analysis?
  • PSP Exam Question 32

    What is the primary difference between the arrow diagramming method (ADM) and the precedence diagramming method (PDM)?
  • PSP Exam Question 33

    Using the normal schedule, theoretically construct a hammock for activities 6001-6003. What is the duration of the hammock?
  • PSP Exam Question 34

    If all other work proceeds according to the Baseline plan, how many times will the critical path change?
  • PSP Exam Question 35

    The best source of project risk or opportunities is: