PSP Exam Question 31
You are retained by a contractor who asks you to perform a simple as-planned versus as-built analysis (APAB) of a large hydro-electric dam project that took more than five years to complete. Your analysis will form the basis of a change order that requests a time extension. You suggest using a different methodology for quantifying the delay. Which of the following reasons for recommending a different analysis does NOT apply to a simple APAB analysis?
PSP Exam Question 32
What is the primary difference between the arrow diagramming method (ADM) and the precedence diagramming method (PDM)?
PSP Exam Question 33
Using the normal schedule, theoretically construct a hammock for activities 6001-6003. What is the duration of the hammock?
PSP Exam Question 34
If all other work proceeds according to the Baseline plan, how many times will the critical path change?


PSP Exam Question 35
The best source of project risk or opportunities is:
