BA2 Exam Question 56
Refer to the Exhibit.

AM Ltd. makes and sells a single product for which the standard cost information is as follows:
* Budgeted production for the period is 30000 units.
* The actual results for the period were as follows:

What is the variable overhead expenditure variance?

AM Ltd. makes and sells a single product for which the standard cost information is as follows:
* Budgeted production for the period is 30000 units.
* The actual results for the period were as follows:

What is the variable overhead expenditure variance?
BA2 Exam Question 57
Refer to the Exhibit.

PD manufactures a product in a process operation. Normal loss is 5% of input and occurs at the end of the process. The following data is available for the month of August:
Scrapped units have no value.
There was no opening or closing work in progress for August.
What is the value of the abnormal gain in August?

PD manufactures a product in a process operation. Normal loss is 5% of input and occurs at the end of the process. The following data is available for the month of August:
Scrapped units have no value.
There was no opening or closing work in progress for August.
What is the value of the abnormal gain in August?
BA2 Exam Question 58
The direct labour efficiency variance is:
BA2 Exam Question 59
The standard material content of 1 unit of PAJ is £200 (8Kg at £25 per Kg).
During Period 5, 1300 Kg of materials were purchased at a total cost of £35000 and were used to produce 170 units of PAJ.
What was the materials price variance for Period 5?
During Period 5, 1300 Kg of materials were purchased at a total cost of £35000 and were used to produce 170 units of PAJ.
What was the materials price variance for Period 5?
BA2 Exam Question 60
Refer to the exhibit.

A company issued its production budget based on an anticipated output of 800 units. Actual output was 1000 units. The details of the costs are shown below:
The budget volume variance was:

A company issued its production budget based on an anticipated output of 800 units. Actual output was 1000 units. The details of the costs are shown below:
The budget volume variance was: