PK0-004 Exam Question 261
A software development project is struggling with a certain technology that is unknown to the project team. A project manager has received a third-party proposal to transfer the risk. Which of the following should the project manager do NEXT?
PK0-004 Exam Question 262
When developing a project schedule, which of the following tools would be MOST beneficial?
PK0-004 Exam Question 263
A project manager has an opportunity to add a highly skilled expert to the team who can increase the probability of the project's success.
Which of the following risk strategies should the project manager adopt?
Which of the following risk strategies should the project manager adopt?
PK0-004 Exam Question 264
There are four parallel paths on a network diagram. The summary duration of each path is below:
A, C, G: 10 weeks
A, B, F: 8 weeks
D, E, H: 12 weeks
D, B, F: 7 weeks
Which of the following tasks are on the critical path?
A, C, G: 10 weeks
A, B, F: 8 weeks
D, E, H: 12 weeks
D, B, F: 7 weeks
Which of the following tasks are on the critical path?
PK0-004 Exam Question 265
The PMO is responsible for: (Choose two.)