PK0-004 Exam Question 201

Which of the following events would MOST likely merit immediate communication to all project stakeholders?
(Choose two.)
  • PK0-004 Exam Question 202

    A project manager has been assigned a project with a budget of $50,000. Three change requests are submitted during execution that will increase the overall project cost to $60,000. Which of the following steps should the project manager perform NEXT?
  • PK0-004 Exam Question 203

    There are four parallel paths on a network diagram. The summary duration of each path is below:
    A, C, G: 10 weeks
    A, B, F: 8 weeks
    D, E, H: 12 weeks
    D, B, F: 7 weeks
    Which of the following tasks are on the critical path?
  • PK0-004 Exam Question 204

    Which of the following is a reason for assessing risk in a project?
  • PK0-004 Exam Question 205

    A sponsor requests that the project team shorten the completion of a project by two months to give the sales team more leverage in renegotiating the contract with the client. The budgeted time is 500 hours, and the projected earned value is $30,000.

    Which of the following represents the cost variance for both project completions?