PK0-004 Exam Question 286

A program manager informs a project manager that a new, high-priority project has been approved and will need the current project's resources before the scheduled project close date. The project team meets and determines that the project should be fast-tracked.
Which of the following documents should the project team reference to fast-track the project? (Choose two.)
  • PK0-004 Exam Question 287

    Which of the following is the MOST likely target audience to be notified of the achievement of a key milestone in a project schedule?
  • PK0-004 Exam Question 288

    When a risk event occurs, which of the following documents is BEST suited for recording and tracking new items corresponding to the risk?
  • PK0-004 Exam Question 289

    When forming a project team, there are a number of phases.
    When a project team is productive and effective this phase is known as which of the following?
  • PK0-004 Exam Question 290

    In a Scrum retrospective, which of the following categories are used to classify the feedback from the team?