PK0-004 Exam Question 336

A company has updated the method it uses to initiate projects. The company requires
RFPs from three vendors, and low and high bids must be rejected to determine the selected vendor.
Which of the following terms describe this requirement?
  • PK0-004 Exam Question 337

    A new high-priority project is assigned to the project manager with a fully formed budget, deadline, and scope.
    The project manager is creating the project schedule.

    Which of the following calculations accurately shows the critical path?
  • PK0-004 Exam Question 338

    A project manager is trying to ensure the quality of the design and reduce the number of potential defects. The project manager would like to use the fishbone diagram to perform this analysis.
    This type of modeling relies on:
  • PK0-004 Exam Question 339

    A sponsor requests that the project team shorten the completion of a project by two months to give the sales team more leverage in renegotiating the contract with the client. The budgeted time is 500 hours, and the projected earned value is $30,000.

    Which of the following represents the cost variance for both project completions?
  • PK0-004 Exam Question 340

    When developing a project schedule, which of the following resources is the BEST to estimate task duration?