PK0-400 Exam Question 16
Which of the following is the MOST likely target audience to be notified of the achievement of a key milestone in a project schedule?
PK0-400 Exam Question 17
A carpenter on a project team reports there is insufficient time to accomplish tasks on schedule.
Which of the following is the FIRST step the project manager should take?
Which of the following is the FIRST step the project manager should take?
PK0-400 Exam Question 18
Team members have reported that meetings are poorly attended and unproductive.
Which of the following steps can the project manager take to make the meetings more productive?
Which of the following steps can the project manager take to make the meetings more productive?
PK0-400 Exam Question 19
Which of the following are examples of organizational change? (Choose two.)
PK0-400 Exam Question 20
Two team members are arguing over two different approaches to complete a task. The project manager listens to both sides, determines neither approach will work, and directs the team members to use a third option.
This type of conflict resolution is known as:
This type of conflict resolution is known as: