PK0-400 Exam Question 1

A project manager is assigned to a project and has not had a handover meeting with the previous project manager. The new project manager is reviewing the percent of project completion, schedule progress, and budget constraints.
Which of the following documents should the project manager use to obtain this information?
  • PK0-400 Exam Question 2

    A company has determined it does not have the in-house capability to perform a project and wants to procure third-party services.
    Which of the following documents will the company MOST likely release FIRST?
  • PK0-400 Exam Question 3

    The project manager has noticed a vendor is not performing in accordance with the SLA.
    Which of the following items should the project manager use to highlight the vendor's areas of poor performance?
  • PK0-400 Exam Question 4

    Which of the following measurements would give the project manager the BEST estimate of the total cost of an active project?
  • PK0-400 Exam Question 5

    A project manager is unsure if the quality of a deliverable from a SME meets specifications.
    Which of the following is the BEST way for the project manager to address the issue?