- Home
- Construction Specifications Institute
- CDT
- ConstructionSpecificationsInstitute.CDT.v2026-03-18.q59 Practice Test (Page 6)
CDT Exam Question 21
When is decommissioning required for a facility?
Correct Answer: B
Comprehensive and Detailed Explanation From Exact Extract (CSI-based)
In CSI's description of the facility life cycle, the last phase is decommissioning. This phase occurs when a facility is taken out of service because it is no longer needed for its original operations, has reached the end of its useful life, or is being prepared for conversion to a different use. The emphasis is on the facility no longer being required for its intended operations, not strictly on demolition or permanent abandonment.
* Decommissioning tasks can include: removing or securing systems, handling hazardous materials, salvaging components, planning for demolition, or preparing the facility for a different use.
* Because decommissioning can precede demolition, adaptive reuse, or other end-of-life actions, it is triggered when the facility is no longer needed for operations.
Option B captures this definition accurately.
Options A and C are too narrow: demolition or permanent disuse are possible outcomes of decommissioning but not the only reasons it is required. Option D (change of ownership) does not automatically require decommissioning; a facility can continue operating normally under a new owner.
Relevant CSI references (no links):
* CSI Project Delivery Practice Guide - Facility Life Cycle chapter (discussion of operations, maintenance, and decommissioning).
* CSI CDT Body of Knowledge - overview of project phases including decommissioning.
In CSI's description of the facility life cycle, the last phase is decommissioning. This phase occurs when a facility is taken out of service because it is no longer needed for its original operations, has reached the end of its useful life, or is being prepared for conversion to a different use. The emphasis is on the facility no longer being required for its intended operations, not strictly on demolition or permanent abandonment.
* Decommissioning tasks can include: removing or securing systems, handling hazardous materials, salvaging components, planning for demolition, or preparing the facility for a different use.
* Because decommissioning can precede demolition, adaptive reuse, or other end-of-life actions, it is triggered when the facility is no longer needed for operations.
Option B captures this definition accurately.
Options A and C are too narrow: demolition or permanent disuse are possible outcomes of decommissioning but not the only reasons it is required. Option D (change of ownership) does not automatically require decommissioning; a facility can continue operating normally under a new owner.
Relevant CSI references (no links):
* CSI Project Delivery Practice Guide - Facility Life Cycle chapter (discussion of operations, maintenance, and decommissioning).
* CSI CDT Body of Knowledge - overview of project phases including decommissioning.
CDT Exam Question 22
In what project stage does the architect/engineer obtain and document the owner's decisions about specific products and systems?
Correct Answer: B
Within CSI's project delivery framework, the Design stage (which includes schematic design and design development) is where the architect/engineer (A/E) works with the owner to evaluate options, select specific systems, and record decisions that will later be fully detailed in the construction documents.
CSI's project-phase descriptions (as presented in the CSI Project Delivery Practice Guide and CDT study materials) explain the stages roughly as follows (paraphrased, not verbatim):
* Project Conception: The owner defines a need or opportunity, explores whether a project is warranted, and considers general feasibility. The focus is on defining the reason for the project, not picking specific products or systems.
* Programming: The owner's requirements and objectives are documented-space needs, performance criteria, budget, schedule, and qualitative expectations. At this point, needs and performance requirements for systems (e.g., "energy-efficient HVAC," "durable flooring") are identified, but not necessarily specific named products or system configurations.
* Design:
* Schematic Design: General design concepts, overall configuration, and preliminary system approaches are developed; the owner begins making more concrete decisions.
* Design Development: The A/E and consultants refine and confirm decisions about specific systems, materials, and assemblies, and these decisions are documented so they can be incorporated into specifications and drawings.
* Construction Documents: The A/E takes those already-made decisions and fully documents them in coordinated drawings and specifications, but this phase is not usually where the majority of decisions about which specific products and systems to use are first obtained; instead, it formalizes and details what was already decided in Design.
CSI's CDT content emphasizes that during Design Development, the A/E "confirms and documents owner decisions about materials, products, and systems" so that these can be translated into clear contract documents during the Construction Documents phase. That activity-obtaining and documenting the owner's decisions about specific products and systems-is core to the Design stage, making Option B correct.
Why the other options are not correct under CSI's framework:
* A. Construction documentationIn the Construction Documents phase, the A/E develops the detailed drawings and specifications based on decisions made earlier. Changes and additional decisions can occur here, but CSI treats the primary "obtaining and documenting owner choices" as a Design-stage responsibility; the CD phase is about formalizing and coordinating them into contract documents.
* C. Project conceptionAt conception, there often isn't an A/E contracted yet, and the owner is still deciding whether to proceed at all. Product and system decisions would be far too early and poorly defined at this point.
* D. ProgrammingProgramming focuses on what the facility must do, not on exactly how via specific products or named systems. It defines performance and functional requirements (e.g., acoustical needs, energy performance) but typically stops short of selecting specific manufacturers or detailed system configurations.
Key CSI-aligned references (no links):
* CSI Project Delivery Practice Guide - chapters on project phases (Programming, Design, Construction Documents) and owner/A/E responsibilities.
* CSI CDT Body of Knowledge - sections on the Design phase and decision-making responsibilities for products and systems.
CSI's project-phase descriptions (as presented in the CSI Project Delivery Practice Guide and CDT study materials) explain the stages roughly as follows (paraphrased, not verbatim):
* Project Conception: The owner defines a need or opportunity, explores whether a project is warranted, and considers general feasibility. The focus is on defining the reason for the project, not picking specific products or systems.
* Programming: The owner's requirements and objectives are documented-space needs, performance criteria, budget, schedule, and qualitative expectations. At this point, needs and performance requirements for systems (e.g., "energy-efficient HVAC," "durable flooring") are identified, but not necessarily specific named products or system configurations.
* Design:
* Schematic Design: General design concepts, overall configuration, and preliminary system approaches are developed; the owner begins making more concrete decisions.
* Design Development: The A/E and consultants refine and confirm decisions about specific systems, materials, and assemblies, and these decisions are documented so they can be incorporated into specifications and drawings.
* Construction Documents: The A/E takes those already-made decisions and fully documents them in coordinated drawings and specifications, but this phase is not usually where the majority of decisions about which specific products and systems to use are first obtained; instead, it formalizes and details what was already decided in Design.
CSI's CDT content emphasizes that during Design Development, the A/E "confirms and documents owner decisions about materials, products, and systems" so that these can be translated into clear contract documents during the Construction Documents phase. That activity-obtaining and documenting the owner's decisions about specific products and systems-is core to the Design stage, making Option B correct.
Why the other options are not correct under CSI's framework:
* A. Construction documentationIn the Construction Documents phase, the A/E develops the detailed drawings and specifications based on decisions made earlier. Changes and additional decisions can occur here, but CSI treats the primary "obtaining and documenting owner choices" as a Design-stage responsibility; the CD phase is about formalizing and coordinating them into contract documents.
* C. Project conceptionAt conception, there often isn't an A/E contracted yet, and the owner is still deciding whether to proceed at all. Product and system decisions would be far too early and poorly defined at this point.
* D. ProgrammingProgramming focuses on what the facility must do, not on exactly how via specific products or named systems. It defines performance and functional requirements (e.g., acoustical needs, energy performance) but typically stops short of selecting specific manufacturers or detailed system configurations.
Key CSI-aligned references (no links):
* CSI Project Delivery Practice Guide - chapters on project phases (Programming, Design, Construction Documents) and owner/A/E responsibilities.
* CSI CDT Body of Knowledge - sections on the Design phase and decision-making responsibilities for products and systems.
CDT Exam Question 23
The three types of commissioning include systems and equipment commissioning, building envelope commissioning, and what other process?
Correct Answer: D
CSI defines commissioning as a quality-focused process that verifies the facility and its systems meet the Owner's Project Requirements (OPR). In the Project Delivery Practice Guide, commissioning is categorized into three broad types (paraphrased):
* Systems and equipment commissioning - verifying that HVAC, electrical, plumbing, life safety, and other building systems perform as intended.
* Building envelope commissioning - verifying performance of the exterior enclosure, including air
/water infiltration, thermal performance, and durability.
* Total project commissioning (also called whole-building or total building commissioning) - extending commissioning to the entire project, including design, construction, and operational aspects, integrating envelope, systems, and other building components.
Given that the question already lists "systems and equipment commissioning" and "building envelope commissioning," the missing third category described by CSI is "total project commissioning", which corresponds to Option D.
Why the other options are not correct:
* A. Mechanical commissioning - This is a subset of systems and equipment commissioning (focused on HVAC/mechanical systems), not one of CSI's three overarching categories.
* B. Facility commissioning - While the term might be used informally, CSI's categorized terminology in the CDT body of knowledge is "total project commissioning" rather than "facility commissioning."
* C. Process commissioning - This term is more common in industrial process industries and is not identified by CSI as one of the three principal commissioning categories for building projects.
CSI References (no links):
* CSI Project Delivery Practice Guide - sections on commissioning types and scope (total project, systems and equipment, building envelope).
* Systems and equipment commissioning - verifying that HVAC, electrical, plumbing, life safety, and other building systems perform as intended.
* Building envelope commissioning - verifying performance of the exterior enclosure, including air
/water infiltration, thermal performance, and durability.
* Total project commissioning (also called whole-building or total building commissioning) - extending commissioning to the entire project, including design, construction, and operational aspects, integrating envelope, systems, and other building components.
Given that the question already lists "systems and equipment commissioning" and "building envelope commissioning," the missing third category described by CSI is "total project commissioning", which corresponds to Option D.
Why the other options are not correct:
* A. Mechanical commissioning - This is a subset of systems and equipment commissioning (focused on HVAC/mechanical systems), not one of CSI's three overarching categories.
* B. Facility commissioning - While the term might be used informally, CSI's categorized terminology in the CDT body of knowledge is "total project commissioning" rather than "facility commissioning."
* C. Process commissioning - This term is more common in industrial process industries and is not identified by CSI as one of the three principal commissioning categories for building projects.
CSI References (no links):
* CSI Project Delivery Practice Guide - sections on commissioning types and scope (total project, systems and equipment, building envelope).
CDT Exam Question 24
What four considerations are included in site selection programming?
Correct Answer: B
In CSI/CDT programming and early project decision-making, the classic four primary project considerations are:
* Function - What the facility must do; the operational and performance requirements.
* Form - The physical configuration and appearance: size, shape, spatial relationships, and aesthetic character.
* Economy - The financial aspects: project budget, life-cycle cost, operating costs, and economic constraints.
* Time - Project and site timing: required completion date, phasing, and schedule constraints.
These four are used in programming and early planning (including site selection and site programming) to structure owner-designer discussions and decisions. During site selection programming, the owner and design team evaluate how different sites support the project's required function, allow appropriate form, meet economic constraints, and fit within time (schedule and phasing) limitations.
This four-part framework-Function, Form, Economy, Time-matches Option B exactly.
Why the other options are incorrect:
All three incorrect options are variations that re-label or partially capture the same ideas but do not use the standard terminology as defined in CSI/CDT references:
* A. Use, space, funds, date
* "Use" # function
* "Space" # form
* "Funds" # economy
* "Date" # timeWhile conceptually similar, CSI's established terminology for programming and site selection is Function, Form, Economy, Time, not this wording.
* C. Purpose, shape, cost, scheduleAgain, these loosely correspond to function, form, economy, and time, but CSI uses the more formal terms that appear in its programming discussions and CDT content:
Function, Form, Economy, Time.
* D. Goal, condition, budget, calendarThese terms are more generic and do not match the recognized four-part framework used in CDI/CDT materials for programming and site selection.
CSI / CDT-aligned references (no links):
* CSI Project Delivery Practice Guide - chapters on Programming and Planning, including the function-form-economy-time framework used in early decision-making and site selection.
* CDT Body of Knowledge - owner's project requirements and programming considerations.
* Function - What the facility must do; the operational and performance requirements.
* Form - The physical configuration and appearance: size, shape, spatial relationships, and aesthetic character.
* Economy - The financial aspects: project budget, life-cycle cost, operating costs, and economic constraints.
* Time - Project and site timing: required completion date, phasing, and schedule constraints.
These four are used in programming and early planning (including site selection and site programming) to structure owner-designer discussions and decisions. During site selection programming, the owner and design team evaluate how different sites support the project's required function, allow appropriate form, meet economic constraints, and fit within time (schedule and phasing) limitations.
This four-part framework-Function, Form, Economy, Time-matches Option B exactly.
Why the other options are incorrect:
All three incorrect options are variations that re-label or partially capture the same ideas but do not use the standard terminology as defined in CSI/CDT references:
* A. Use, space, funds, date
* "Use" # function
* "Space" # form
* "Funds" # economy
* "Date" # timeWhile conceptually similar, CSI's established terminology for programming and site selection is Function, Form, Economy, Time, not this wording.
* C. Purpose, shape, cost, scheduleAgain, these loosely correspond to function, form, economy, and time, but CSI uses the more formal terms that appear in its programming discussions and CDT content:
Function, Form, Economy, Time.
* D. Goal, condition, budget, calendarThese terms are more generic and do not match the recognized four-part framework used in CDI/CDT materials for programming and site selection.
CSI / CDT-aligned references (no links):
* CSI Project Delivery Practice Guide - chapters on Programming and Planning, including the function-form-economy-time framework used in early decision-making and site selection.
* CDT Body of Knowledge - owner's project requirements and programming considerations.
CDT Exam Question 25
What is the basis of payment for a contract negotiated between an owner and a contractor for a fixed price?
Correct Answer: A
CSI's treatment of methods of payment / contract pricing (as used in standard owner-contractor agreements and CDT content) includes several common bases of payment:
* Stipulated Sum (Lump Sum)
* The contractor agrees to provide the work for a single fixed price.
* The price does not change except through formal changes to the work (change orders).
* This is the classic "fixed-price" contract form.
* Unit Price
* The contractor is paid based on measured quantities of work completed multiplied by agreed unit rates.
* Final cost depends on actual quantities installed, not a single fixed total.
* Cost-Plus-Fee
* The owner reimburses actual cost of the work (labor, materials, equipment, etc.) plus a fee (fixed or percentage) as contractor's compensation.
* The final cost is not fixed; it varies with actual costs incurred.
* Cost-Plus-Fee with Guaranteed Maximum Price (GMP)
* A variation of cost-plus where the total reimbursable cost plus fee is capped at a guaranteed maximum.
* Still not the same as a straightforward fixed lump sum; the basis is cost reimbursement up to a cap.
The question specifically asks: "for a fixed price." In CSI and standard contract terminology, "fixed price"
= "stipulated sum" (or lump sum). That is:
* The owner and contractor negotiate a single dollar amount for the entire scope of work;
* The contractor's compensation is that stipulated sum, adjusted only by approved changes.
Why the other options are not correct:
* B. Unit price - The total cost is not fixed at the time of contracting; it depends on actual installed quantities.
* C. Cost-plus-fee - Costs are reimbursed; final price is open-ended and therefore not fixed.
* D. Cost-plus-fee with guaranteed maximum price - This sets a cap, but the actual final cost is not a single fixed price; it is "actual cost plus fee" up to the GMP.
Therefore, the correct basis of payment for a fixed-price contract is Stipulated sum (Option A), consistent with CSI's classification of contract types and standard owner-contractor agreements.
Key CSI References (titles only, no links):
* CSI Project Delivery Practice Guide - sections on "Basis of Payment" and contract pricing methods (stipulated sum, unit price, cost-plus, GMP).
* CSI CDT Body of Knowledge - Contract Types and Methods of Payment.
* Standard owner-contractor agreements discussed in CSI materials (e.g., stipulated sum as the fixed- price form).
* Stipulated Sum (Lump Sum)
* The contractor agrees to provide the work for a single fixed price.
* The price does not change except through formal changes to the work (change orders).
* This is the classic "fixed-price" contract form.
* Unit Price
* The contractor is paid based on measured quantities of work completed multiplied by agreed unit rates.
* Final cost depends on actual quantities installed, not a single fixed total.
* Cost-Plus-Fee
* The owner reimburses actual cost of the work (labor, materials, equipment, etc.) plus a fee (fixed or percentage) as contractor's compensation.
* The final cost is not fixed; it varies with actual costs incurred.
* Cost-Plus-Fee with Guaranteed Maximum Price (GMP)
* A variation of cost-plus where the total reimbursable cost plus fee is capped at a guaranteed maximum.
* Still not the same as a straightforward fixed lump sum; the basis is cost reimbursement up to a cap.
The question specifically asks: "for a fixed price." In CSI and standard contract terminology, "fixed price"
= "stipulated sum" (or lump sum). That is:
* The owner and contractor negotiate a single dollar amount for the entire scope of work;
* The contractor's compensation is that stipulated sum, adjusted only by approved changes.
Why the other options are not correct:
* B. Unit price - The total cost is not fixed at the time of contracting; it depends on actual installed quantities.
* C. Cost-plus-fee - Costs are reimbursed; final price is open-ended and therefore not fixed.
* D. Cost-plus-fee with guaranteed maximum price - This sets a cap, but the actual final cost is not a single fixed price; it is "actual cost plus fee" up to the GMP.
Therefore, the correct basis of payment for a fixed-price contract is Stipulated sum (Option A), consistent with CSI's classification of contract types and standard owner-contractor agreements.
Key CSI References (titles only, no links):
* CSI Project Delivery Practice Guide - sections on "Basis of Payment" and contract pricing methods (stipulated sum, unit price, cost-plus, GMP).
* CSI CDT Body of Knowledge - Contract Types and Methods of Payment.
* Standard owner-contractor agreements discussed in CSI materials (e.g., stipulated sum as the fixed- price form).
- Latest Upload
- 135Oracle.1D0-1057-25-D.v2026-06-03.q29
- 269NAHQ.CPHQ.v2026-06-03.q396
- 252CompTIA.220-1201.v2026-06-03.q196
- 154GIAC.GCFE.v2026-06-03.q78
- 148HIMSS.CPHIMS.v2026-06-03.q45
- 231Google.Professional-Cloud-Architect.v2026-06-03.q165
- 150HP.HPE7-A09.v2026-06-02.q48
- 160ACDIS.CCDS-O.v2026-06-02.q56
- 137Microsoft.AB-730.v2026-06-02.q31
- 209ASQ.CSSBB.v2026-06-02.q130
[×]
Download PDF File
Enter your email address to download ConstructionSpecificationsInstitute.CDT.v2026-03-18.q59 Practice Test
