D-VXR-DY-01 Exam Question 146
When validating the completed VxRail PEQ, you note the following VLANs in the configuration:\
- VxRailManagement - VLAN 120
- vSAN - VLAN 121
- vMotion - VLAN 122
- Servers - VLAN 204
- NetManagement - VLAN 208
Which command should you use to validate that the VLANs are configured on each Dell EMC ToR switch?
- VxRailManagement - VLAN 120
- vSAN - VLAN 121
- vMotion - VLAN 122
- Servers - VLAN 204
- NetManagement - VLAN 208
Which command should you use to validate that the VLANs are configured on each Dell EMC ToR switch?
D-VXR-DY-01 Exam Question 147
An implementation engineer is performing a precheck on a VxRail cluster before expansion. During validation, they find out that the host is not compatible.
Use the VxRail simulator to describe why the host is Incompatible.
Note: It is necessary to close (x) the simulator window before you can select a response to this question.



Use the VxRail simulator to describe why the host is Incompatible.
Note: It is necessary to close (x) the simulator window before you can select a response to this question.



D-VXR-DY-01 Exam Question 148
What is a requirement for the vSAN Data-at-Rest Encryption?
D-VXR-DY-01 Exam Question 149
What are three planning considerations when using a customer-supplied vCenter Server? (Choose three.)
D-VXR-DY-01 Exam Question 150
An existing Dell EMC customer wants to deploy a new VxRail cluster on premise. Each node of the new cluster will be configured with a single disk group containing one 1.6 TB Flash drive for the capacity tier. The customer plans on using mirroring and needs to have at least 2 TB of usable capacity in the vSAN datastore.
What is the minimum number of VxRail nodes required?
What is the minimum number of VxRail nodes required?