ASM Exam Question 6
During a Sprint Planning, a team has picked three User Stories:
Story 1 - 5 Story Points
Story 2 - 8 Story Points
Story 3 - 3 Story Points
At the end of the Sprint, the team has completed Story 1 and Story 3 and the Product Owner accepts these.
The team has almost completed Story 2 but there are a few bugs identified in acceptance tests.
What is the Velocity of this team?
Story 1 - 5 Story Points
Story 2 - 8 Story Points
Story 3 - 3 Story Points
At the end of the Sprint, the team has completed Story 1 and Story 3 and the Product Owner accepts these.
The team has almost completed Story 2 but there are a few bugs identified in acceptance tests.
What is the Velocity of this team?
ASM Exam Question 7
Inexperienced Agile teams tend to overestimate how much they will achieve in the first Sprint.
Which project management activity will be most important in this case?
Which project management activity will be most important in this case?
ASM Exam Question 8
You are a project manager for a midsize software company, which still uses the Waterfall model. Your customer wants a new software project.
When should you consider the use of Agile?
When should you consider the use of Agile?
ASM Exam Question 9
A Scrum Team is supposed to deliver potentially snippable software at the end of each Sprint. During the last Sprint the Team did not deliver a potentially shippable increment.
The correct question to ask is: "What can we do to make sure we do better in the next Sprint?" Who is responsible for making sure this question asked?
The correct question to ask is: "What can we do to make sure we do better in the next Sprint?" Who is responsible for making sure this question asked?
ASM Exam Question 10
Which information Radiator can the team use best during the Sprint to track the work?