HPE0-S22 Exam Question 81

An architect proposes an HPE Moonshot solution to a customer. The customer informs the architect that the data center switches can only provide four 40GbE ports per rack.
How should the architect modify the proposed solution so that each rack meets the requirement?
HPE0-S22 Exam Question 82
A customer has a large Oracle-based ERP solution that runs on HPUX and multiple rx2800 i2 servers. The customer plans to move to an open source solution to reduce operating expenses. The customer needs the ability to deliver incremental capacity and needs to avoid incremental Oracle licensing costs.
Which HPE Server solution will help meet the customer's needs?
Which HPE Server solution will help meet the customer's needs?
HPE0-S22 Exam Question 83
Which discussion point describes a Tier I approach to datacenter redundancy levels?
HPE0-S22 Exam Question 84
A customer has 1,000 virtual machines that run on VMware ESXi servers. The customer is concerned that some of the virtual machines may be oversized, which could affect the other virtual machines.
Which HPE product should the architect recommend to help the customer with infrastructure sizing, to improve efficiency, and to reduce cost?
Which HPE product should the architect recommend to help the customer with infrastructure sizing, to improve efficiency, and to reduce cost?
HPE0-S22 Exam Question 85
An architect proposes an HPE Moonshot solution with three HPE Moonshot 1500 Chassis as follows:
- one chassis with 30 m710 cartridges
- two chassis with 30 m800 cartridges each
The customer wants to change the solution to use two HPE Moonshot 1500 chassis as follows:
- one chassis with 30 m710 cartridges and 15 m800 cartridges
- one chassis with 45 m800 cartridges
What should the architect explain to the customer?
- one chassis with 30 m710 cartridges
- two chassis with 30 m800 cartridges each
The customer wants to change the solution to use two HPE Moonshot 1500 chassis as follows:
- one chassis with 30 m710 cartridges and 15 m800 cartridges
- one chassis with 45 m800 cartridges
What should the architect explain to the customer?