HPE0-V28 Exam Question 66
Your customer needs a compute solution. Their aging data center can only supply 5kW per rack, which is below the 15kW required for your planned solution.
Which change could you recommend to satisfy the requirement while maintaining the planned solution's level of performance? (Choose two.)
Which change could you recommend to satisfy the requirement while maintaining the planned solution's level of performance? (Choose two.)