H12-421 Exam Question 51
The NetCol5000-A35kW indoor unit installation needs to be connected to the zero line.
H12-421 Exam Question 52
In the installation scenario where the indoor unit is higher than the outdoor unit, the oil trap must be set.
H12-421 Exam Question 53
In the process of disconnecting the battery pack switch, if there are multiple sets of batteries, first disconnect the main switch between the battery pack and the UPS, and then disconnect the switch of each battery pack.
H12-421 Exam Question 54
Neteco can't centrally and uniformly manage data center infrastructure across multiple geographies
H12-421 Exam Question 55
When installing the power line on the UPS5000-E, if there are different sources on the main side, you need to remove the copper bars connected to the bypass and the main circuit, and then connect the main circuit and the bypass input respectively.