H12-421 Exam Question 51

The NetCol5000-A35kW indoor unit installation needs to be connected to the zero line.
  • H12-421 Exam Question 52

    In the installation scenario where the indoor unit is higher than the outdoor unit, the oil trap must be set.
  • H12-421 Exam Question 53

    In the process of disconnecting the battery pack switch, if there are multiple sets of batteries, first disconnect the main switch between the battery pack and the UPS, and then disconnect the switch of each battery pack.
  • H12-421 Exam Question 54

    Neteco can't centrally and uniformly manage data center infrastructure across multiple geographies
  • H12-421 Exam Question 55

    When installing the power line on the UPS5000-E, if there are different sources on the main side, you need to remove the copper bars connected to the bypass and the main circuit, and then connect the main circuit and the bypass input respectively.