H12-425-ENU Exam Question 91

To modify the plane view of the ECC800 micromodule, need to log in to the Web to operate with administrator privileges.
  • H12-425-ENU Exam Question 92

    The operation noise of the NetCol5000-A air conditioning unit is abnormal. It should be checked whether the compressor, fan, pipeline, etc. are fixed normally and there is looseness.
  • H12-425-ENU Exam Question 93

    In the case of normal mains, the UPS battery in inverter mode may be executed ( ). (Multiple choice)
  • H12-425-ENU Exam Question 94

    Before installing the indoor unit of NetCol5000-A, we should remove the sheet metals from the compressor.
  • H12-425-ENU Exam Question 95

    Three sets of 9Ah battery packs are connected in parallel and connected to UPS2000-G-6kVA. What is the battery capacity set?