IIA-CIA-Part2 Exam Question 376
An organization's internal auditors are reviewing production costs at a gas-powered electrical generating plant.
They identify a serious problem with the accuracy of carbon dioxide emissions reported to the environmental regulatory agency, due to computer errors. The auditors should immediately report the concern to:
They identify a serious problem with the accuracy of carbon dioxide emissions reported to the environmental regulatory agency, due to computer errors. The auditors should immediately report the concern to:
IIA-CIA-Part2 Exam Question 377
A retail company uses a computer program that matches electronic vendor invoices with the applicable purchase orders and receiving information, which are also maintained electronically.
If an invoice does not match the other items within predefined ranges, a report is generated and sent to the accounts payable department for further investigation. All of the applicable documents are electronically marked, cross-referenced, and retained in open files. Both an integrated test facility and a systems control audit review file (SCARF) have been included in the system.
An auditor wants to determine the extent to which items are not matched at year end and to investigate the potential causes of the unmatched items. Which of the following audit procedures would be most effective in determining the items to investigate?
If an invoice does not match the other items within predefined ranges, a report is generated and sent to the accounts payable department for further investigation. All of the applicable documents are electronically marked, cross-referenced, and retained in open files. Both an integrated test facility and a systems control audit review file (SCARF) have been included in the system.
An auditor wants to determine the extent to which items are not matched at year end and to investigate the potential causes of the unmatched items. Which of the following audit procedures would be most effective in determining the items to investigate?
IIA-CIA-Part2 Exam Question 378
A company has recently incurred significant cost overruns on one of its construction projects. Management suspects that these overruns were caused by the contractor improperly accounting for costs related to contract change orders. Which of the following procedures would be appropriate for testing this suspicion?
I.Verify that the contractor has not charged change orders with costs that have already been billed to the original contract.
II.
Determine if the contractor has billed for original contract work that was canceled as a result of change orders.
III.
Verify that the change orders were properly approved by management.
I.Verify that the contractor has not charged change orders with costs that have already been billed to the original contract.
II.
Determine if the contractor has billed for original contract work that was canceled as a result of change orders.
III.
Verify that the change orders were properly approved by management.
IIA-CIA-Part2 Exam Question 379
Risk assessments can vary in format, but generally include:
1. A description of identified risks.
2. Tests of audit controls.
3. A system of rating risks.
4. Sample size identification.
1. A description of identified risks.
2. Tests of audit controls.
3. A system of rating risks.
4. Sample size identification.
IIA-CIA-Part2 Exam Question 380
Due to the expanded role of internal audit in the organization, the chief audit executive (CAE) of a construction company decides to employ the services of an outsourced audit service provider to augment the internal audit staff. What does the CAE need to consider in determining whether the outsourced audit service provider possesses the necessary knowledge, skills and other competencies to perform an audit engagement?