CGEIT Exam Question 111

A marketing enterprise is considering procuring customer information to more accurately target customer communications and increase sales. The data has a very high cost to the enterprise. Which of the following would provide the MOST comprehensive view into the potential value to the organization?
  • CGEIT Exam Question 112

    Melody is the project manager for her organization. She has created a risk response to conduct more tests on the software her project is creating. The identified risk that prompted this response was that the software is mission-critical and must be flawless before it can be put into product. What type of a risk response has Melody used in this scenario?
  • CGEIT Exam Question 113

    Which of the following should be the PRIMARY consideration for an enterprise when prioritizing IT projects?
  • CGEIT Exam Question 114

    The PRIMARY objective of building outcome measures is to:
  • CGEIT Exam Question 115

    Which of the following objectives are used by the system to decrease costs or revenues?