CGEIT Exam Question 31

You are the project manager for your company and a new change request has been approved for your project.
This change request, however, has introduced several new risks to the project. You have communicated these risk events and the project stakeholders understand the possible effects these risks could have on your project.
You elect to create a mitigation response for the identified risk events. Where will you record the mitigation response?
  • CGEIT Exam Question 32

    Which of the following steps of IT governance program decides on the highest priority projects that will help to improve the management and governance of the significant gap areas?
  • CGEIT Exam Question 33

    Which of the following has PRIMARY responsibility to define the requirements for IT service levels for the enterprise?
  • CGEIT Exam Question 34

    The MOST important aspect of an IT governance framework to ensure that IT supports repeatable business processes is:
  • CGEIT Exam Question 35

    Which of the following processes uses statistical evidences to determine progress toward specific defined organizational objectives?