CISA-CN Exam Question 161
確定 IT 資源支出是否與規劃專案支出一致的最佳方法是什麼?
Correct Answer: A
The best method to determine if IT resource spending is aligned with planned project spending is earned value analysis (EVA). EVA is a technique that compares the actual cost, schedule, and scope of a project with the planned or budgeted values. EVA can help to measure the project progress and performance, and identify any variances or deviations from the baseline plan1.
EVA uses three basic values to calculate the project status: planned value (PV), earned value (EV), and actual cost (AC). PV is the amount of work that was expected to be completed by a certain date, according to the project plan. EV is the amount of work that was actually completed by that date, measured in terms of the budgeted cost. AC is the amount of money that was actually spent to complete the work by that date1.
By comparing these values, EVA can determine if the project is on track, ahead, or behind schedule and budget. EVA can also calculate various indicators, such as cost variance (CV), schedule variance (SV), cost performance index (CPI), and schedule performance index (SPI), to quantify the magnitude and direction of the variances. EVA can also forecast the future performance and completion of the project, based on the current trends and assumptions1.
The other options are not as effective as EVA in determining if IT resource spending is aligned with planned project spending. Option B, return on investment (ROI) analysis, is a technique that evaluates the profitability or efficiency of an investment, by comparing the benefits or revenues with the costs. ROI analysis can help to justify or prioritize a project, but it does not measure the actual progress or performance of the project against the plan2. Option C, Gantt chart, is a tool that displays the tasks, durations, dependencies, and milestones of a project in a graphical format. Gantt chart can help to plan and monitor a project schedule, but it does not show the actual cost or scope of the project3. Option D, critical path analysis, is a technique that identifies the longest sequence of tasks or activities that must be completed on time for the project to finish on schedule. Critical path analysis can help to optimize and control a project schedule, but it does not account for the actual cost or scope of the project4.
References:
* Earned Value Analysis & Management (EVA/EVM) - Definition & Formulae1
* Return on Investment (ROI) Formula2
* What Is a Gantt Chart?3
* Critical Path Method for Project Management
EVA uses three basic values to calculate the project status: planned value (PV), earned value (EV), and actual cost (AC). PV is the amount of work that was expected to be completed by a certain date, according to the project plan. EV is the amount of work that was actually completed by that date, measured in terms of the budgeted cost. AC is the amount of money that was actually spent to complete the work by that date1.
By comparing these values, EVA can determine if the project is on track, ahead, or behind schedule and budget. EVA can also calculate various indicators, such as cost variance (CV), schedule variance (SV), cost performance index (CPI), and schedule performance index (SPI), to quantify the magnitude and direction of the variances. EVA can also forecast the future performance and completion of the project, based on the current trends and assumptions1.
The other options are not as effective as EVA in determining if IT resource spending is aligned with planned project spending. Option B, return on investment (ROI) analysis, is a technique that evaluates the profitability or efficiency of an investment, by comparing the benefits or revenues with the costs. ROI analysis can help to justify or prioritize a project, but it does not measure the actual progress or performance of the project against the plan2. Option C, Gantt chart, is a tool that displays the tasks, durations, dependencies, and milestones of a project in a graphical format. Gantt chart can help to plan and monitor a project schedule, but it does not show the actual cost or scope of the project3. Option D, critical path analysis, is a technique that identifies the longest sequence of tasks or activities that must be completed on time for the project to finish on schedule. Critical path analysis can help to optimize and control a project schedule, but it does not account for the actual cost or scope of the project4.
References:
* Earned Value Analysis & Management (EVA/EVM) - Definition & Formulae1
* Return on Investment (ROI) Formula2
* What Is a Gantt Chart?3
* Critical Path Method for Project Management
CISA-CN Exam Question 162
下列哪一項可以為管理階層提供最合理的保證,即新的資料倉儲將滿足組織的需求?
Correct Answer: A
A data warehouse is a centralized repository of data that is collected from various sources and organized for analysis and reporting purposes. A data warehouse can help an organization gain insights into its business performance, trends, and opportunities. However, building a data warehouse requires careful planning, design, and implementation to ensure that it meets the needs of the organization.
One of the best practices that would provide management with the most reasonable assurance that a new data warehouse will meet the needs of the organization is A. Integrating data requirements into the system development life cycle (SDLC). The SDLC is a framework that defines the phases and activities involved in developing a software system, such as planning, analysis, design, testing, deployment, and maintenance1. By integrating data requirements into the SDLC, an organization can ensure that the data warehouse is aligned with the business objectives and expectations, and that it delivers value to the end users.
Some of the benefits of integrating data requirements into the SDLC are:
* It helps to identify and prioritize the key business questions and metrics that the data warehouse should support2.
* It helps to define and validate the data sources, models, structures, and quality standards that the data warehouse should follow3.
* It helps to design and implement the data integration, transformation, and loading processes that the data warehouse should use4.
* It helps to test and verify the functionality, performance, and accuracy of the data warehouse before deploying it to production.
* It helps to monitor and maintain the data warehouse after deployment and incorporate feedback and changes as needed.
One of the best practices that would provide management with the most reasonable assurance that a new data warehouse will meet the needs of the organization is A. Integrating data requirements into the system development life cycle (SDLC). The SDLC is a framework that defines the phases and activities involved in developing a software system, such as planning, analysis, design, testing, deployment, and maintenance1. By integrating data requirements into the SDLC, an organization can ensure that the data warehouse is aligned with the business objectives and expectations, and that it delivers value to the end users.
Some of the benefits of integrating data requirements into the SDLC are:
* It helps to identify and prioritize the key business questions and metrics that the data warehouse should support2.
* It helps to define and validate the data sources, models, structures, and quality standards that the data warehouse should follow3.
* It helps to design and implement the data integration, transformation, and loading processes that the data warehouse should use4.
* It helps to test and verify the functionality, performance, and accuracy of the data warehouse before deploying it to production.
* It helps to monitor and maintain the data warehouse after deployment and incorporate feedback and changes as needed.
CISA-CN Exam Question 163
對於部署零信任架構的任何網路設計,下列哪一項應該是主要關注點?
Correct Answer: D
CISA-CN Exam Question 164
在大容量、即時系統中,持續監控和分析事務處理最有效的技術是:
Correct Answer: C
Transaction tagging is a technique by which transactions are marked with unique identifiers or headers and traced through the system using agents or sensors at each processing point1. Transaction tagging allows for continuous monitoring and analysis of transaction processing in a high-volume, real-time system by providing visibility into the performance, availability, and reliability of each transaction and its components1. Transaction tagging can also help to identify and isolate errors, bottlenecks, anomalies, and security issues in the system1.
CISA-CN Exam Question 165
IS 審計員正在對醫療機構進行實體安全審計,並發現病患照護區域內有閉路電視 (CCTV) 系統。下列哪一項是最令人擔憂的?
Correct Answer: B
The greatest concern with finding closed-circuit television (CCTV) systems located in a patient care area is that there are no notices indicating recording is in progress. This is because CCTV systems in healthcare settings can pose a threat to the privacy and confidentiality of patients, staff, and visitors, especially in sensitive areas where personal or medical information may be exposed. According to the government's Surveillance camera code of practice1, CCTV operators must be as transparent as possible in the use of CCTV, and inform people that they are being recorded by using clear and visible signs. The signs should also provide contact details of the CCTV operator and the purpose of the surveillance. By providing notices, CCTV operators can comply with data protection law and respect the rights and expectations of individuals.
Option B is correct because the lack of notices indicating recording is in progress is a clear violation of the Surveillance camera code of practice1, which applies to local authorities and the police, and is encouraged to be adopted by other CCTV operators in England and Wales. The code also applies to Scotland, along with the National Strategy for Public Space CCTV2. The code is intended to be used in conjunction with the guidance provided by the Information Commissioner's Office (ICO)3, which applies across the UK. The ICO states that CCTV operators must inform people that they are being recorded by using prominent signs at the entrance of the CCTV zone and reinforcing this with further signs inside the area.
Option A is incorrect because cameras not being monitored 24/7 is not the greatest concern, as it does not necessarily affect the privacy and confidentiality of individuals. CCTV systems may have different purposes and objectives, such as deterring or monitoring crime, enhancing security, or improving patient care.
Depending on the purpose, CCTV systems may not require constant monitoring, but rather periodic review or analysis. However, CCTV operators should still ensure that they have adequate security measures to protect the CCTV systems from unauthorized access or tampering.
Option C is incorrect because the retention period for video recordings being undefined is not the greatest concern, as it does not directly affect the privacy and confidentiality of individuals. However, CCTV operators should still define and document their retention policy, and ensure that they do not keep video recordings for longer than necessary, unless they are needed for a specific purpose or as evidence. The retention period should be based on a clear and justifiable rationale, and comply with data protection law and industry guidelines.
Option D is incorrect because there being no backups of the videos is not the greatest concern, as it does not affect the privacy and confidentiality of individuals. However, CCTV operators should still consider having backups of their videos, especially if they are needed for a specific purpose or as evidence. Backups can help to prevent data loss or corruption due to system failures, disasters, or malicious attacks. Backups should also be stored securely and encrypted to prevent unauthorized access or disclosure.
Option B is correct because the lack of notices indicating recording is in progress is a clear violation of the Surveillance camera code of practice1, which applies to local authorities and the police, and is encouraged to be adopted by other CCTV operators in England and Wales. The code also applies to Scotland, along with the National Strategy for Public Space CCTV2. The code is intended to be used in conjunction with the guidance provided by the Information Commissioner's Office (ICO)3, which applies across the UK. The ICO states that CCTV operators must inform people that they are being recorded by using prominent signs at the entrance of the CCTV zone and reinforcing this with further signs inside the area.
Option A is incorrect because cameras not being monitored 24/7 is not the greatest concern, as it does not necessarily affect the privacy and confidentiality of individuals. CCTV systems may have different purposes and objectives, such as deterring or monitoring crime, enhancing security, or improving patient care.
Depending on the purpose, CCTV systems may not require constant monitoring, but rather periodic review or analysis. However, CCTV operators should still ensure that they have adequate security measures to protect the CCTV systems from unauthorized access or tampering.
Option C is incorrect because the retention period for video recordings being undefined is not the greatest concern, as it does not directly affect the privacy and confidentiality of individuals. However, CCTV operators should still define and document their retention policy, and ensure that they do not keep video recordings for longer than necessary, unless they are needed for a specific purpose or as evidence. The retention period should be based on a clear and justifiable rationale, and comply with data protection law and industry guidelines.
Option D is incorrect because there being no backups of the videos is not the greatest concern, as it does not affect the privacy and confidentiality of individuals. However, CCTV operators should still consider having backups of their videos, especially if they are needed for a specific purpose or as evidence. Backups can help to prevent data loss or corruption due to system failures, disasters, or malicious attacks. Backups should also be stored securely and encrypted to prevent unauthorized access or disclosure.
- Other Version
- 416ISACA.CISA-CN.v2026-09-15.q708
- 3316ISACA.CISA-CN.v2026-05-19.q615
- 1439ISACA.CISA-CN.v2026-05-16.q320
- 3187ISACA.CISA-CN.v2025-12-21.q601
- Latest Upload
- 118Salesforce.Slack-Con-201.v2026-09-17.q40
- 146AAPC.CPC.v2026-09-17.q182
- 125NetworkAppliance.NS0-094.v2026-09-17.q70
- 115PaloAltoNetworks.XSIAM-Engineer.v2026-09-17.q28
- 154Workday.Workday-Pro-Integrations.v2026-09-16.q48
- 151Cisco.350-801.v2026-09-16.q298
- 141SAP.C_ARCIG.v2026-09-16.q35
- 416ISACA.CISA-CN.v2026-09-15.q708
- 164EMC.NCA.v2026-09-15.q38
- 167Netskope.NSK300.v2026-09-14.q35
[×]
Download PDF File
Enter your email address to download ISACA.CISA-CN.v2025-12-17.q626 Practice Test