CISA Exam Question 246
An IT balanced scorecard is PRIMARILY used for:
Correct Answer: B
An IT balanced scorecard is primarily used for measuring IT strategic performance. An IT balanced scorecard is a framework that translates the IT strategy into measurable objectives, indicators, targets, and initiatives across four perspectives: financial, customer, internal process, and learning and growth. An IT balanced scorecard helps to monitor and evaluate how well the IT function is delivering value to the organization, achieving its strategic goals, and improving its capabilities and competencies. The other options are not the primary uses of an IT balanced scorecard, because they either focus on specific aspects of IT rather than the overall performance, or they are not directly related to the IT strategy. References: CISA Review Manual (Digital Version)1, Chapter 1, Section 1.2.3
CISA Exam Question 247
During recent post-implementation reviews, an IS auditor has noted that several deployed applications are not being used by the business. The MOST likely cause would be the lack of:
Correct Answer: D
CISA Exam Question 248
Which of the following is MOST important for an IS auditor to confirm when reviewing an organization's plans to implement robotic process automation (RPA> to automate routine business tasks?
Correct Answer: A
The most important thing for an IS auditor to confirm when reviewing an organization's plans to implement robotic process automation (RPA) to automate routine business tasks is that the end-to-end process is understood and documented. This is because RPA involves the use of software robots or digital workers to mimic human actions and execute predefined rules and workflows. Therefore, it is essential that the IS auditor verifies that the organization has a clear and accurate understanding of the current state of the process, the desired state of the process, the inputs and outputs, the exceptions and errors, the roles and responsibilities, and the performance measures12. Without a properdocumentation of the end-to-end process, the organizationmay face challenges in designing, developing, testing, deploying, and monitoring the RPA solution3. References: 1: CISA ReviewManual (Digital Version), Chapter 4: Information Systems Operations and Business Resilience, Section 4.2: IT Service Delivery and Support, page 211 2:CISA Online Review Course, Module 4: Information Systems Operations and Business Resilience, Lesson 4.2: IT Service Delivery and Support 3: ISACA Journal Volume 5, 2019, Article: Robotic Process Automation: Benefits, Risks and Controls
CISA Exam Question 249
Which of the following is the MOST appropriate indicator of change management effectiveness?
Correct Answer: D
Change management is the process of planning, implementing, monitoring, and evaluating changes to an organization's information systems and related components. Change management aims to ensure that changes are aligned with the business objectives, minimize risks and disruptions, and maximize benefits and value.
One of the key aspects of change management is measuring its effectiveness, which means assessing whether the changes have achieved the desired outcomes and met the expectations of the stakeholders. There are various indicators that can be used to measure change management effectiveness, such as time, cost, quality, scope, satisfaction, and performance.
Among the four options given, the most appropriate indicator of change management effectiveness is the number of incidents resulting from changes. An incident is an unplanned event or interruption that affects the normal operation or service delivery of an information system. Incidents can be caused by various factors, such as errors, defects, failures, malfunctions, or malicious attacks. Incidents can have negative impacts on the organization, such as loss of data, productivity, reputation, or revenue.
The number of incidents resulting from changes is a direct measure of how well the changes have been planned, implemented, monitored, and evaluated. A high number of incidents indicates that the changes have not been properly tested, verified, communicated, or controlled. A low number of incidents indicates that the changes have been executed smoothly and successfully. Therefore, the number of incidents resulting from changes reflects the quality and effectiveness of the change management process.
The other three options are not as appropriate indicators of change management effectiveness as the number of incidents resulting from changes. The time lag between changes to the configuration and the update of records is a measure of how timely and accurate the configuration management process is. Configuration management is a subset of change management that focuses on identifying, documenting, and controlling the configuration items (CIs) that make up an information system. The time lag between changes and updates of documentation materials is a measure of how well the documentation process is aligned with the change management process. Documentation is an important aspect of change management that provides information and guidance to the stakeholders involved in or affected by the changes. The number of system software changes is a measure of how frequently and extensively the system software is modified or updated. System software changes are a type of change that affects the operating system, middleware, or utilities that support an information system.
While these three indicators are relevant and useful for measuring certain aspects of change management, they do not directly measure the outcomes or impacts of the changes on the organization. They are more related to the inputs or activities of change management than to its outputs or results. Therefore, they are not as appropriate indicators of change management effectiveness as the number of incidents resulting from changes.
References:
Metrics for Measuring Change Management - Prosci
How to Measure Change Management Effectiveness: Metrics, Tools & Processes Metrics for Measuring Change Management 2023 - Zendesk
One of the key aspects of change management is measuring its effectiveness, which means assessing whether the changes have achieved the desired outcomes and met the expectations of the stakeholders. There are various indicators that can be used to measure change management effectiveness, such as time, cost, quality, scope, satisfaction, and performance.
Among the four options given, the most appropriate indicator of change management effectiveness is the number of incidents resulting from changes. An incident is an unplanned event or interruption that affects the normal operation or service delivery of an information system. Incidents can be caused by various factors, such as errors, defects, failures, malfunctions, or malicious attacks. Incidents can have negative impacts on the organization, such as loss of data, productivity, reputation, or revenue.
The number of incidents resulting from changes is a direct measure of how well the changes have been planned, implemented, monitored, and evaluated. A high number of incidents indicates that the changes have not been properly tested, verified, communicated, or controlled. A low number of incidents indicates that the changes have been executed smoothly and successfully. Therefore, the number of incidents resulting from changes reflects the quality and effectiveness of the change management process.
The other three options are not as appropriate indicators of change management effectiveness as the number of incidents resulting from changes. The time lag between changes to the configuration and the update of records is a measure of how timely and accurate the configuration management process is. Configuration management is a subset of change management that focuses on identifying, documenting, and controlling the configuration items (CIs) that make up an information system. The time lag between changes and updates of documentation materials is a measure of how well the documentation process is aligned with the change management process. Documentation is an important aspect of change management that provides information and guidance to the stakeholders involved in or affected by the changes. The number of system software changes is a measure of how frequently and extensively the system software is modified or updated. System software changes are a type of change that affects the operating system, middleware, or utilities that support an information system.
While these three indicators are relevant and useful for measuring certain aspects of change management, they do not directly measure the outcomes or impacts of the changes on the organization. They are more related to the inputs or activities of change management than to its outputs or results. Therefore, they are not as appropriate indicators of change management effectiveness as the number of incidents resulting from changes.
References:
Metrics for Measuring Change Management - Prosci
How to Measure Change Management Effectiveness: Metrics, Tools & Processes Metrics for Measuring Change Management 2023 - Zendesk
CISA Exam Question 250
in a post-implantation Nation review of a recently purchased system it is MOST important for the iS auditor to determine whether the:
Correct Answer: C
The most important thing for the IS auditor to determine in a post-implementation review of a recently purchased system is whether the user requirements were met. User requirements are the specifications and expectations of the users of the system, such as the features, functions, performance, quality, and security of the system. User requirements are usually defined and documented in the early stages of the system acquisition process, such as in the request for proposal (RFP) or the contract. User requirements are also used as the basis for testing and evaluating the system before and after implementation.
Determining whether the user requirements were met can help the IS auditor assess whether the system is fit for purpose and delivers value and benefits to the users and the organization. Determining whether the user requirements were met can also help the IS auditor identify any gaps, issues, or problems with the system that may affect its functionality, usability, or reliability. Determining whether the user requirements were met can also help the IS auditor provide feedback and recommendations for improvement or enhancement of the system.
Stakeholder expectations were identified is not the most important thing for the IS auditor to determine in a post-implementation review of a recently purchased system, but rather a prerequisite or input for it.
Stakeholder expectations are the needs and wants of the various parties who have an interest or influence in the system, such as users, managers, customers, suppliers, regulators, or auditors. Stakeholder expectations are usually identified and analyzed in the initial stages of the system acquisition process, such as in the feasibility study or the business case. Stakeholder expectations are also used as inputs for defining and prioritizing the user requirements.
Vendor product offered a viable solution is not the most important thing for the IS auditor to determine in a post-implementation review of a recently purchased system, but rather an outcome or result of it. Vendor product is the system that is provided by an external supplier or service provider to meet the user requirements. Vendor product offered a viable solution means that the vendor product satisfied or exceeded the user requirements and delivered value and benefits to the users and organization. Vendor product offered a viable solution can be determined by comparing and evaluating the user requirements and the vendor product performance and quality.
Test scenarios reflected operating activities is not the most important thing for the IS auditor to determine in a post-implementation review of a recently purchased system, but rather a factor or criterion for it. Test scenarios are sets of conditions or situations that are used to test and verify whether the system meets the user requirements. Test scenarios reflected operating activities means that test scenarios simulated or replicated real-world scenarios that occur during normal operations of business processes or functions that use or depend on the system. Test scenarios reflected operating activities can help ensure that test results are valid, reliable, and relevant.
References:
Post Implementation Review: How to conduct and its Benefits 1
Post-implementation reviews - Department of Prime Minister and Cabinet 2 How To Conduct A Post Implementation Audit of Your RecentlyInstalled System 3
Determining whether the user requirements were met can help the IS auditor assess whether the system is fit for purpose and delivers value and benefits to the users and the organization. Determining whether the user requirements were met can also help the IS auditor identify any gaps, issues, or problems with the system that may affect its functionality, usability, or reliability. Determining whether the user requirements were met can also help the IS auditor provide feedback and recommendations for improvement or enhancement of the system.
Stakeholder expectations were identified is not the most important thing for the IS auditor to determine in a post-implementation review of a recently purchased system, but rather a prerequisite or input for it.
Stakeholder expectations are the needs and wants of the various parties who have an interest or influence in the system, such as users, managers, customers, suppliers, regulators, or auditors. Stakeholder expectations are usually identified and analyzed in the initial stages of the system acquisition process, such as in the feasibility study or the business case. Stakeholder expectations are also used as inputs for defining and prioritizing the user requirements.
Vendor product offered a viable solution is not the most important thing for the IS auditor to determine in a post-implementation review of a recently purchased system, but rather an outcome or result of it. Vendor product is the system that is provided by an external supplier or service provider to meet the user requirements. Vendor product offered a viable solution means that the vendor product satisfied or exceeded the user requirements and delivered value and benefits to the users and organization. Vendor product offered a viable solution can be determined by comparing and evaluating the user requirements and the vendor product performance and quality.
Test scenarios reflected operating activities is not the most important thing for the IS auditor to determine in a post-implementation review of a recently purchased system, but rather a factor or criterion for it. Test scenarios are sets of conditions or situations that are used to test and verify whether the system meets the user requirements. Test scenarios reflected operating activities means that test scenarios simulated or replicated real-world scenarios that occur during normal operations of business processes or functions that use or depend on the system. Test scenarios reflected operating activities can help ensure that test results are valid, reliable, and relevant.
References:
Post Implementation Review: How to conduct and its Benefits 1
Post-implementation reviews - Department of Prime Minister and Cabinet 2 How To Conduct A Post Implementation Audit of Your RecentlyInstalled System 3
- Other Version
- 1109ISACA.CISA.v2026-09-25.q633
- 4963ISACA.CISA.v2025-12-09.q630
- 19978ISACA.CISA.v2025-06-20.q647
- 7971ISACA.CISA.v2025-06-11.q606
- 5138ISACA.CISA.v2023-03-04.q272
- 3902ISACA.CISA.v2022-10-31.q203
- 3670ISACA.CISA.v2022-03-29.q126
- 123ISACA.Examprepaway.CISA.v2022-02-10.by.barret.126q.pdf
- 11423ISACA.CISA.v2021-11-29.q567
- 36ISACA.Actualvce.CISA.v2021-08-31.by.ralap.101q.pdf
- Latest Upload
- 156InsuranceLicensing.PA-Title-Insurance-Agent.v2026-09-30.q30
- 164EMC.NCP-MCI.v2026-09-30.q46
- 213Microsoft.GH-200.v2026-09-29.q65
- 263PECB.ISO-9001-Lead-Auditor.v2026-09-29.q115
- 204Oracle.1Z0-1080-26.v2026-09-29.q59
- 210Microsoft.GH-500.v2026-09-29.q56
- 238Splunk.SPLK-1003.v2026-09-29.q96
- 302ISQI.CTFL_Syll_4.0.v2026-09-28.q175
- 226Cisco.300-445.v2026-09-28.q61
- 193Hitachi.HCE-5910.v2026-09-28.q53
[×]
Download PDF File
Enter your email address to download ISACA.CISA.v2025-12-02.q704 Practice Test