CRISC Exam Question 1

What is the PRIMARY objective difference between an internal and an external risk management assessment reviewer?
  • CRISC Exam Question 2

    You are the project manager of your project. You have to analyze various project risks. You have opted for quantitative analysis instead of qualitative risk analysis. What is the MOST significant drawback of using quantitative analysis over qualitative risk analysis?
  • CRISC Exam Question 3

    Which of the following is NOT true for Key Risk Indicators?
  • CRISC Exam Question 4

    You are the project manager in your enterprise. You have identified occurrence of risk event in your enterprise. You have pre-planned risk responses. You have monitored the risks that had occurred. What is the immediate step after this monitoring process that has to be followed in response to risk events?
  • CRISC Exam Question 5

    What is the MAIN purpose of designing risk management programs?