Kelly is the project manager of the NNQ Project for her company. This project will last for one year and has a budget of $350,000. Kelly is working with her project team and subject matter experts to begin the risk response planning process. What are the two inputs that Kelly would need to begin the plan risk response process?
Correct Answer: D
Explanation/Reference: Explanation: The only two inputs for the risk response planning are the risk register and the risk management plan. The plan risk response project management process aims to reduce the threats to the project objectives and to increase opportunities. It follows the perform qualitative risk analysis process and perform quantitative risk analysis process. Plan risk response process includes the risk response owner to take the job for each agreed-to and funded risk response. This process addresses the risks by their priorities, schedules the project management plan as required, and inserts resources and activities into the budget. The inputs to the plan risk response process are as follows: Risk register Risk management plan Incorrect Answers: B: Kelly will not need the risk response plan until monitoring and controlling the project. C: The results of risk analysis will help Kelly prioritize the risks, but this information will be recorded in the risk register. D: Kelly needs the risk register and the risk management plan as the input. The power to assign risk responses is not necessarily needed by Kelly.
CRISC Exam Question 307
Which of the following will BEST help in communicating strategic risk priorities?
Correct Answer: A
CRISC Exam Question 308
You are the project manager of the KJH Project and are working with your project team to plan the risk responses. Consider that your project has a budget of $500,000 and is expected to last six months. Within the KJH Project you have identified a risk event that has a probability of .70 and has a cost impact of $350,000. When it comes to creating a risk response for this event what is the risk exposure of the event that must be considered for the cost of the risk response?
Correct Answer: D
Section: Volume B Explanation/Reference: Explanation: The risk exposure for this event is found by multiplying the risk impact by the risk probability. Risk Exposure is a straightforward estimate that gives a numeric value to a risk, enabling different risks to be compared. Risk Exposure of any given risk = Probability of risk occurring x impact of risk event = 0.70 * 350,000 = 245,000 Incorrect Answers: A: $350,000 is the impact of the risk event. B: $500,000 is the project's budget. C: $850,000 is the project's budget and the risk's impact.
CRISC Exam Question 309
An organization is implementing encryption for data at rest to reduce the risk associated with unauthorized access. Which of the following MUST be considered to assess the residual risk?
Correct Answer: D
Section: Volume D
CRISC Exam Question 310
Which of the following processes addresses the risks by their priorities, schedules the project management plan as required, and inserts resources and activities into the budget?
Correct Answer: B
is incorrect. Qualitative analysis is the definition of risk factors in terms of high/medium/low or a numeric scale (1 to 10). Hence it determines the nature of risk on a relative scale. Some of the qualitative methods of risk analysis are: Scenario analysis- This is a forward-looking process that can reflect risk for a given point in time. Risk Control Self -assessment (RCSA) - RCSA is used by enterprises (like banks) for the identification and evaluation of operational risk exposure. It is a logical first step and assumes that business owners and managers are closest to the issues and have the most expertise as to the source of the risk. RCSA is a constructive process in compelling business owners to contemplate, and then explain, the issues at hand with the added benefit of increasing their accountability.