CRISC Exam Question 26

You are the project manager of project for a client. The client has promised your company a bonus, if the project is completed early. After studying the project work, you elect to crash the project in order to realize the early end date. This is an example of what type of risk response?
  • CRISC Exam Question 27

    A risk practitioner notices that a particular key risk indicator (KRI) has remained below its established trigger point for an extended period of time. Which of the following should be done FIRST?
  • CRISC Exam Question 28

    John works as a project manager for BlueWell Inc. He is determining which risks can affect the project. Which of the following inputs of the identify risks process is useful in identifying risks associated to the time allowances for the activities or projects as a whole, with a width of the range indicating the degrees of risk?
  • CRISC Exam Question 29

    Which of the following is the GREATEST risk associated with the use of data analytics?
  • CRISC Exam Question 30

    Which of the following would be considered a vulnerability?