CRISC Exam Question 171

Thomas is a key stakeholder in your project. Thomas has requested several changes to the project scope for the project you are managing.
Upon review of the proposed changes, you have discovered that these new requirements are laden with risks and you recommend to the change control board that the changes be excluded from the project scope. The change control board agrees with you. What component of the change control system communicates the approval or denial of a proposed change request?
  • CRISC Exam Question 172

    You are the project manager of GHT project. You have selected appropriate Key Risk Indicators for your project. Now, you need to maintain those Key Risk Indicators. What is the MOST important reason to maintain Key Risk Indicators?
  • CRISC Exam Question 173

    An organization is considering allowing users to access company data from their personal devices. Which of the following is the MOST important factor when assessing the risk?
  • CRISC Exam Question 174

    Which of the following is the BEST approach for determining whether a risk action plan is effective?
  • CRISC Exam Question 175

    Which of the following resources is MOST helpful to a risk practitioner when updating the likelihood rating in the risk register?