CRISC Exam Question 81

You are the project manager of the KJH Project and are working with your project team to plan the risk responses. Consider that your project has a budget of $500,000 and is expected to last six months. Within the KJH Project you have identified a risk event that has a probability of .70 and has a cost impact of $350,000.
When it comes to creating a risk response for this event what is the risk exposure of the event that must be considered for the cost of the risk response?
  • CRISC Exam Question 82

    A new regulator/ requirement imposes severe fines for data leakage involving customers' personally identifiable information (Pll). The risk practitioner has recommended avoiding the risk. Which of the following actions would BEST align with this recommendation?
  • CRISC Exam Question 83

    You are the project manager of RFT project. You have identified a risk that the enterprise's IT system and application landscape is so complex that, within a few years, extending capacity will become difficult and maintaining software will become very expensive. To overcome this risk, the response adopted is re- architecture of the existing system and purchase of new integrated system. In which of the following risk prioritization options would this case be categorized?
  • CRISC Exam Question 84

    The MAIN goal of the risk analysis process is to determine the:
  • CRISC Exam Question 85

    Which of the following is the way to verify control effectiveness?