CRISC Exam Question 31
You are the project manager of GHT project. Your project utilizes a machine for production of goods. This machine has the specification that if its temperature would rise above 450 degree Fahrenheit then it may result in burning of windings. So, there is an alarm which blows when machine's temperature reaches 430 degree Fahrenheit and the machine is shut off for 1 hour. What role does alarm contribute here?
CRISC Exam Question 32
Which of the following would provide executive management with the BEST information to make risk decisions as a result of a risk assessment?
CRISC Exam Question 33
Which of the following is an administrative control?
CRISC Exam Question 34
Determining if organizational risk is tolerable requires:
CRISC Exam Question 35
Which of the following is the MAIN reason for analyzing risk scenarios?