CRISC Exam Question 481
Of the following, who should be responsible for determining the inherent risk rating of an application?
CRISC Exam Question 482
You are the project manager of the NHH Project. You are working with the project team to create a plan to document the procedures to manage risks throughout the project. This document will define how risks will be identified and quantified. It will also define how contingency plans will be implemented by the project team. What document do you and your team is creating in this scenario?
CRISC Exam Question 483
You are the project manager for BlueWell Inc. You have noticed that the risk level in your project increases above the risk tolerance level of your enterprise. You have applied several risk responses. Now you have to update the risk register in accordance to risk response process. All of the following are included in the risk register except for which item?
CRISC Exam Question 484
You are the project manager of GHT project. You identified a risk of noncompliance with regulations due to missing of a number of relatively simple procedures.
The response requires creating the missing procedures and implementing them. In which of the following risk response prioritization should this case be categorized?
The response requires creating the missing procedures and implementing them. In which of the following risk response prioritization should this case be categorized?
CRISC Exam Question 485
An application owner has specified the acceptable downtime in the event of an incident to be much lower than the actual time required for the response team to recover the application. Which of the following should be the NEXT course of action?