CRISC Exam Question 516
A risk owner has accepted a high-impact risk because the control was adversely affecting process efficiency.
Before updating the risk register, it is MOST important for the risk practitioner to:
Before updating the risk register, it is MOST important for the risk practitioner to:
Correct Answer: D
A risk owner is the individual who is accountable for the management of a specific risk. A risk owner can decide to accept a high-impact risk if the control that mitigates the risk is adversely affecting the process efficiency. However, before updating the risk register, which is a document that records and tracks the identified risks and their responses, it is most important for the risk practitioner to obtain approval from senior management. Senior management is the group of executives who have the authority and responsibility for the strategic direction and performance of the organization. Obtaining approval from senior management can help ensure that the risk acceptance decision is aligned with the organization's risk appetite and policies, and that the potential consequences of the high-impact risk are understood and accepted by the top-level decision makers. Obtaining approval from senior management can also help communicate and justify the risk acceptance decision to other stakeholders, such as regulators, auditors, customers, etc., and avoid any conflicts or misunderstandings that may arise from the risk acceptance decision. References = Why Assigning a Risk Owner is Important and How to Do It Right, Risk Ownership: A brief guide, Creating a Risk Register: All You Need to Know.
CRISC Exam Question 517
Which of the following should be management's PRIMARY consideration when approving risk response action plans?
Correct Answer: C
The management's primary consideration when approving risk response action plans should be the changes in residual risk after implementing the plans. Residual risk is the level of risk that remains after the implementation of risk responses1. It indicates the degree of exposure or uncertainty that the organization still faces, and the potential impact or consequences of the risk events. The management should evaluate the effectiveness and adequacy of the risk responses, and decide whether the residual risk is acceptable or not2. The management should also compare the residual risk with the risk appetite, which is the amount and type of risk that the organization is willing to accept or pursue in order to achieve its objectives3. The management should ensure that the residual risk is aligned with the risk appetite, and that the risk responses are consistent and proportional to the risk level4.
The other options are not the primary consideration when approving risk response action plans, because:
* Ability of the action plans to address multiple risk scenarios is a desirable but not essential criterion for approving risk response action plans. Risk scenarios are hypothetical situations that describe how a risk event could occur and what the consequences could be5. They can help to understand and communicate the nature and impact of the risks, and to design and evaluate the risk responses6. However, not all risk scenarios are equally likely or relevant, and some risk scenarios may be too complex or improbable to address. Therefore, the ability of the action plans to address multiple risk scenarios is not the primary consideration, but rather a secondary or supplementary one.
* Ease of implementing the risk treatment solution is a practical but not critical criterion for approving risk response action plans. Risk treatment is the process of selecting and applying appropriate measures to modify the risk7. It can involve different strategies, such as avoid, reduce, transfer, or accept the risk8. The ease of implementing the risk treatment solution depends on various factors, such as the availability of resources, the feasibility of the solution, or the cooperation of the stakeholders. However, the ease of implementation is not the primary consideration, but rather a supporting or facilitating one.
* Prioritization for implementing the action plans is a useful but not vital criterion for approving risk response action plans. Prioritization is the process of ranking the action plans according to their importance, urgency, or impact. It can help to allocate the resources, schedule the activities, and monitor the progress of the action plans. However, prioritization is not the primary consideration, but rather a subsequent or follow-up one.
References =
* Residual Risk - CIO Wiki
* What is Residual Risk? - Definition from Techopedia
* Risk Appetite - CIO Wiki
* Risk Appetite: What It Is and Why It Matters - Gartner
* Risk Scenarios Toolkit - ISACA
* Risk Scenarios Starter Pack - ISACA
* Risk Treatment - CIO Wiki
* Risk Treatment Plan - CIO Wiki
* [Prioritization - CIO Wiki]
The other options are not the primary consideration when approving risk response action plans, because:
* Ability of the action plans to address multiple risk scenarios is a desirable but not essential criterion for approving risk response action plans. Risk scenarios are hypothetical situations that describe how a risk event could occur and what the consequences could be5. They can help to understand and communicate the nature and impact of the risks, and to design and evaluate the risk responses6. However, not all risk scenarios are equally likely or relevant, and some risk scenarios may be too complex or improbable to address. Therefore, the ability of the action plans to address multiple risk scenarios is not the primary consideration, but rather a secondary or supplementary one.
* Ease of implementing the risk treatment solution is a practical but not critical criterion for approving risk response action plans. Risk treatment is the process of selecting and applying appropriate measures to modify the risk7. It can involve different strategies, such as avoid, reduce, transfer, or accept the risk8. The ease of implementing the risk treatment solution depends on various factors, such as the availability of resources, the feasibility of the solution, or the cooperation of the stakeholders. However, the ease of implementation is not the primary consideration, but rather a supporting or facilitating one.
* Prioritization for implementing the action plans is a useful but not vital criterion for approving risk response action plans. Prioritization is the process of ranking the action plans according to their importance, urgency, or impact. It can help to allocate the resources, schedule the activities, and monitor the progress of the action plans. However, prioritization is not the primary consideration, but rather a subsequent or follow-up one.
References =
* Residual Risk - CIO Wiki
* What is Residual Risk? - Definition from Techopedia
* Risk Appetite - CIO Wiki
* Risk Appetite: What It Is and Why It Matters - Gartner
* Risk Scenarios Toolkit - ISACA
* Risk Scenarios Starter Pack - ISACA
* Risk Treatment - CIO Wiki
* Risk Treatment Plan - CIO Wiki
* [Prioritization - CIO Wiki]
CRISC Exam Question 518
Which of The following BEST represents the desired risk posture for an organization?
Correct Answer: D
The best representation of the desired risk posture for an organization is when the residual risk is lower than the risk tolerance. Residual risk is the remaining risk after the implementation of risk responses or controls.
Risk tolerance is the acceptable level of risk that the organization is willing to take or bear. The desired risk posture is when the organization has reduced the residual risk to a level that is equal to or lower than the risk tolerance, which means that the organization has achieved its risk objectives and is comfortable with the remaining risk exposure. The other options are not the best representation of the desired risk posture, as they indicate that the organization has not effectively managed its risk. Inherent risk is lower than risk tolerance means that the organization has not identified or assessed its risk properly, as inherent risk is the risk before any controls or responses are applied. Operational risk is higher than risk tolerance means that the organization has not implemented or monitored its risk responses or controls adequately, as operational risk is the risk of loss resulting from inadequate or failed internal processes, people, and systems. Accepted risk is higher than risk tolerance means that the organization has not aligned its risk appetite and risk tolerance, as accepted risk is the risk that the organization chooses to retain or take without any further action. References = Risk and Information Systems Control Study Manual, Chapter 2, Section 2.3.1, page 2-
23.
Risk tolerance is the acceptable level of risk that the organization is willing to take or bear. The desired risk posture is when the organization has reduced the residual risk to a level that is equal to or lower than the risk tolerance, which means that the organization has achieved its risk objectives and is comfortable with the remaining risk exposure. The other options are not the best representation of the desired risk posture, as they indicate that the organization has not effectively managed its risk. Inherent risk is lower than risk tolerance means that the organization has not identified or assessed its risk properly, as inherent risk is the risk before any controls or responses are applied. Operational risk is higher than risk tolerance means that the organization has not implemented or monitored its risk responses or controls adequately, as operational risk is the risk of loss resulting from inadequate or failed internal processes, people, and systems. Accepted risk is higher than risk tolerance means that the organization has not aligned its risk appetite and risk tolerance, as accepted risk is the risk that the organization chooses to retain or take without any further action. References = Risk and Information Systems Control Study Manual, Chapter 2, Section 2.3.1, page 2-
23.
CRISC Exam Question 519
Which of the following is the BEST way to quantify the likelihood of risk materialization?
Correct Answer: B
A threat and vulnerability assessment is a process that identifies and evaluates the potential sources and impacts of risk events on an organization's assets, processes, and objectives. It also estimates the probability of occurrence and the severity of consequences for each risk event. A threat and vulnerability assessment is the best way to quantify the likelihood of risk materialization, as it provides a numerical or qualitative measure of the risk exposure and the level of uncertainty associated with the risk scenarios. References = Risk and Information Systems Control Study Manual, Chapter 2, Section 2.2.2, p. 68-69
CRISC Exam Question 520
The implementation of a risk treatment plan will exceed the resources originally allocated for the risk response. Which of the following should be the risk owner's NEXT action?
Correct Answer: C
A risk treatment plan is a document that outlines the actions and resources required to implement the chosen risk response for a specific risk1. A risk response is a strategy or action that is taken or planned to mitigate or eliminate the risk, such as avoiding, transferring, reducing, or accepting the risk2. A risk owner is a person or entity that has the authority and accountability for a risk and its management3. If the implementation of a risk treatment plan will exceed the resources originally allocated for the risk response, the risk owner's next action should be to escalate to senior management, which is the group of senior leaders who have the authority and accountability for the organization's performance and governance4. By escalating to senior management, the risk owner can inform and consult them about the situation and the implications, and seek their guidance and approval for the necessary adjustments or alternatives. Escalating to senior management can also help to ensure that the risk treatment plan is aligned with the organization's strategy, vision, and mission, and that the risk response is consistent with the organization's risk appetite and tolerance5. Performing a risk assessment, accepting the risk of not implementing, and updating the implementation plan are not the best choices for the risk owner's next action, as they do not provide the same level of communication and consultation as escalating to senior management. Performing a risk assessment is a process that involves identifying, analyzing, and evaluating the risks and their potential impacts on the organization's objectives and performance6. Performing a risk assessment can help to update and validate the risk information and the risk treatment plan, but it does not address the issue of the resource shortfall or the stakeholder expectations. Accepting the risk of not implementing is a decision that involves acknowledging and tolerating the risk or its impact without taking any action to reduce or eliminate it7. Accepting the risk of not implementing can help to avoid the additional cost and effort of the risk treatment plan, but it does not consider the potential consequences or the stakeholder interests. Updating the implementation plan is a process that involves revising and modifying the plan for executing the risk treatment plan, such as the scope, schedule, budget, or quality8. Updating the implementation plan can help to reflect the changes and updates in the risk treatment plan, but it does not resolve the problem of the resource gap or the stakeholder approval.
References = 1: Risk Treatment and Response Plans - UNECE2: Risk Response Strategy and Contingency Plans - ProjectManagement.com3: [Risk Ownership - Risk Management] 4: [Senior Management - Definition, Roles and Responsibilities] 5: [Risk Appetite and Tolerance - ISACA] 6: [Risk Assessment - an overview | ScienceDirect Topics] 7: [Risk Acceptance - an overview | ScienceDirect Topics] 8: [Implementation Plan - an overview | ScienceDirect Topics] : [Risk and Information Systems Control Study Manual, Chapter 3: Risk Response, Section 3.1: Risk Response Options, pp. 113-115.] : [Risk and Information Systems Control Study Manual, Chapter 4: Risk and Control Monitoring and Reporting, Section 4.2: Risk Monitoring, pp. 189-191.] :
[Risk and Information Systems Control Study Manual, Chapter 5: Information Systems Control Design and Implementation, Section 5.1: Control Design, pp. 233-235.] : [Risk and Information Systems Control Study Manual, Chapter 5: Information Systems Control Design and Implementation, Section 5.2: Control Implementation, pp. 243-245.] : [Risk and Information Systems Control Study Manual, Chapter 5:
Information Systems Control Design and Implementation, Section 5.3: Control Monitoring and Maintenance, pp. 251-253.]
References = 1: Risk Treatment and Response Plans - UNECE2: Risk Response Strategy and Contingency Plans - ProjectManagement.com3: [Risk Ownership - Risk Management] 4: [Senior Management - Definition, Roles and Responsibilities] 5: [Risk Appetite and Tolerance - ISACA] 6: [Risk Assessment - an overview | ScienceDirect Topics] 7: [Risk Acceptance - an overview | ScienceDirect Topics] 8: [Implementation Plan - an overview | ScienceDirect Topics] : [Risk and Information Systems Control Study Manual, Chapter 3: Risk Response, Section 3.1: Risk Response Options, pp. 113-115.] : [Risk and Information Systems Control Study Manual, Chapter 4: Risk and Control Monitoring and Reporting, Section 4.2: Risk Monitoring, pp. 189-191.] :
[Risk and Information Systems Control Study Manual, Chapter 5: Information Systems Control Design and Implementation, Section 5.1: Control Design, pp. 233-235.] : [Risk and Information Systems Control Study Manual, Chapter 5: Information Systems Control Design and Implementation, Section 5.2: Control Implementation, pp. 243-245.] : [Risk and Information Systems Control Study Manual, Chapter 5:
Information Systems Control Design and Implementation, Section 5.3: Control Monitoring and Maintenance, pp. 251-253.]
- Other Version
- 3129ISACA.CRISC.v2025-01-04.q999
- 1426ISACA.CRISC.v2024-06-13.q683
- 2114ISACA.CRISC.v2024-04-02.q999
- 2709ISACA.CRISC.v2023-07-10.q544
- 5435ISACA.CRISC.v2022-05-25.q338
- 76ISACA.Actual4dump.CRISC.v2022-04-12.by.newman.349q.pdf
- 5243ISACA.CRISC.v2022-02-22.q349
- 5070ISACA.CRISC.v2021-10-27.q295
- 42ISACA.Updatedumps.CRISC.v2021-09-05.by.bonnie.114q.pdf
- Latest Upload
- 323ISACA.CGEIT.v2025-09-19.q537
- 155Fortinet.FCP_FWF_AD-7.4.v2025-09-18.q62
- 156Scrum.SAFe-Practitioner.v2025-09-18.q63
- 146Workday.Workday-Prism-Analytics.v2025-09-17.q17
- 131Oracle.1Z0-1055-24.v2025-09-17.q28
- 129Oracle.1Z1-182.v2025-09-17.q32
- 247Nutanix.NCP-US-6.5.v2025-09-16.q73
- 266Oracle.1z0-071.v2025-09-16.q232
- 204Oracle.1Z1-922.v2025-09-16.q125
- 327CyberArk.PAM-CDE-RECERT.v2025-09-15.q100
[×]
Download PDF File
Enter your email address to download ISACA.CRISC.v2025-08-27.q675 Practice Test