CTAL-TM_Syll2012 Exam Question 1

A chart showing the trend in the lag time from defect reporting to resolution during system testing is also available. The chart shows that the daily closure period is consistently and significantly above the rolling closure period for a long period of the system testing phase.
Almost all defects found during system testing have been related to the system as a whole, not related to single units or integrations issues. Almost all quality risks have been addressed during the unit and integration testing phase and no residual quality risks were present in the integrated system. This has been confirmed by exploratory testing sessions performed during system testing, targeted at finding defects in these quality risk areas.
Based on the given information only, which one of the following areas would you expect to be considered more in the retrospective meeting in order to be improved?
  • CTAL-TM_Syll2012 Exam Question 2

    Which of the following answers describes a factor that may reduce the effort spent when using distributed test teams without negatively affecting system quality?
    K2 1 credit
  • CTAL-TM_Syll2012 Exam Question 3

    Consider a defect report and assume that a part of its lifecycle includes the following states:
    New: Is the initial state
    WorkinG. Means that the developers are addressing the defect in order to produce a fix for the defect Clarification: Means that the developers need more information from the tester to address the defect and produce a fix for the defect and the tester is working to provide this information to the developers Verification: Means that a fix for the defect has been produced and the tester is running the adequate tests to verify whether the fix solves the defect
    CloseD. is the final state
    Which of the following answers represents an invalid sequence of states that can't lead the bug report to the "Closed" state?
    K2 1 credit
  • CTAL-TM_Syll2012 Exam Question 4

    Test Management
    Assume you are managing the system testing phase of a project.
    The system test execution period is scheduled to twenty weeks.
    All tests are manual tests. You are following a risk-driven test approach.
    During the last staff meeting the project manager tells you new deadlines that will not allow completion of all the system tests.
    Which of the following would you expect to be the best way to respond to this situation?
  • CTAL-TM_Syll2012 Exam Question 5

    Test Management
    Assume you are currently working on a project developing a system where functional requirements are very well specified. Unfortunately non-functional requirements do almost not exist.
    You are the Test Manager. You have to choose a technique for test selection that allows testing of non- functional characteristics, especially reliability.
    Which of the following techniques for test selection do you expect being most useful in this scenario?