ATM Exam Question 1

You can count on well-written requirements, but you can't count on an adequate contribution of the stakeholders to the quality risk analysis. You have to mitigate the insufficient contribution of the stakeholders because the risk-based testing approach shall minimize the product risks. Your test team has one expert tester in security testing.
Which of the following test activities would you expect to be the less important in this context?
  • ATM Exam Question 2

    If you are monitoring code coverage during testing to determine what areas still need testing what type of testing is likely occurring?
  • ATM Exam Question 3

    Which of the following information would you expect to be the most useful to perform a
    defect clustering analysis?
    K2 1 credit
  • ATM Exam Question 4

    Consider an information system of a Pay-Tv company based on a SOA architecture.
    The integrated system currently consists of three core systems:
    - a CRM (Customer Relationship Management) system
    - a BRM (Billing and Revenue Management) system
    - a CAS (Conditional Access System) system all of them communicating with SOA Middleware.
    You have been asked to manage the testing activities for the integration of two additional off-the-shelf systems from two different vendors: a SMS (Short Message Service) server and an IVR (Interactive Voice Response) system.
    Assume that there is a high likelihood that the two off-the-shelf systems will be low-quality and that you have a clear proof that the testing performed by the two vendors on their systems has been unsystematic and unprofessional. This obviously leads to higher quality risk for the overall integrated system.
    You are the Test Manager of this project. Your main goal is to plan for testing activities to mitigate this risk.
    Which of the following answers best describes the test activities (assuming it is possible to perform all of them) you should plan for?
  • ATM Exam Question 5

    You are working on a project that is having problems with regressions. Witheach release of software given to the test team. 50% of the defects found are actually regressions.To combat this you have decided to implement test automation.You have given your automation team the following goal
    'Implement lest automation to automate 90% of the manual regression tests before the productrelease date.'' Which of the following is likely an issue with this goal being defined as "SMART?