AZ-900 Exam Question 46
You have 1,000 virtual machines hosted on the Hyper-V hosts in a data center.
You plan to migrate all the virtual machines to an Azure pay-as-you-go subscription.
You need to identify which expenditure model to use for the planned Azure solution.
Which expenditure model should you identify?
You plan to migrate all the virtual machines to an Azure pay-as-you-go subscription.
You need to identify which expenditure model to use for the planned Azure solution.
Which expenditure model should you identify?
AZ-900 Exam Question 47
For each of the following statements, select Yes if the statement is true. Otherwise, select No.
NOTE: Each correct selection is worth one point.

NOTE: Each correct selection is worth one point.

AZ-900 Exam Question 48
What is the longest term you can purchase tor Azure Reserved VM Instances?
AZ-900 Exam Question 49
This question requires that you evaluate the underlined BOLD text to determine if it is correct.
Your company implements Azure policies to automatically add a watermark to Microsoft Word documents that contain credit card information.
Instructions: Review the underlined text. If it makes the statement correct, select "No change is needed". If the statement is incorrect, select the answer choice that makes the statement correct.
Your company implements Azure policies to automatically add a watermark to Microsoft Word documents that contain credit card information.
Instructions: Review the underlined text. If it makes the statement correct, select "No change is needed". If the statement is incorrect, select the answer choice that makes the statement correct.
AZ-900 Exam Question 50
You have an on-premises network that contains several servers.
You plan to migrate all the servers to Azure.
You need to recommend a solution to ensure that some of the servers are available if a single Azure data center goes offline for an extended period.
What should you include in the recommendation?
You plan to migrate all the servers to Azure.
You need to recommend a solution to ensure that some of the servers are available if a single Azure data center goes offline for an extended period.
What should you include in the recommendation?