MB-320 Exam Question 101
A manufacturer uses route operations and job scheduling.
You use a unique calendar for a conveyor line. The company observes a decrease in the number of hours a conveyor line resource is operational due to breakdowns. You must make a temporary change to the number of hours the resource is available.
You need to adjust the efficiency percentage for the conveyor line calendar.
Which three actions should you perform in sequence? To answer, move the appropriate actions from the list of actions to the answer area and arrange them in the correct order.

You use a unique calendar for a conveyor line. The company observes a decrease in the number of hours a conveyor line resource is operational due to breakdowns. You must make a temporary change to the number of hours the resource is available.
You need to adjust the efficiency percentage for the conveyor line calendar.
Which three actions should you perform in sequence? To answer, move the appropriate actions from the list of actions to the answer area and arrange them in the correct order.

MB-320 Exam Question 102
A skateboard manufacturer uses route operations to schedule resources and estimate units per hour. All products use the sample sub assembly item and resource sanding process.
You observe an increase in the number of units a sanding belt resource can produce. The production schedule is now inaccurate due to the number of units the sanding belt line can produce.
You must make a permanent change to the number of units the resource can produce for all future orders.
You need to adjust the process quantity on the route operation.
Which three actions should you perform in sequence? To answer, move the appropriate actions form the list of actions to the answer area and arrange them in the correct order.

You observe an increase in the number of units a sanding belt resource can produce. The production schedule is now inaccurate due to the number of units the sanding belt line can produce.
You must make a permanent change to the number of units the resource can produce for all future orders.
You need to adjust the process quantity on the route operation.
Which three actions should you perform in sequence? To answer, move the appropriate actions form the list of actions to the answer area and arrange them in the correct order.

MB-320 Exam Question 103
Note: This question is part of a series of questions that present the same scenario. Each question in the series contains a unique solution that might meet the stated goals. Some questions sets might have more than one correct solutions, while others might not have a correct solution.
After you answer a question in this section, you will NOT be able to return to it. As a result, these questions will not appear in the review screen.
A manufacturing plant uses Lean process. You plan to outsource a painting operation to a subcontracting vendor. You create a service item named SP-01 to represent the painting service.
You need to create a subcontracting activity for the painting service.
Solution:
1.) Create a purchase agreement for the subcontracting vendor and add SP-01 as the painting service
2.) Create a vendor resource then create a work cell for outsourced painting and add the resource to the work cell
3.) Create a production flow process activity for the painting work cell and add the component to be painted as a picking activity
4.) Create a service term to tie the purchase agreement to the activity Does this solution meet the goal?
After you answer a question in this section, you will NOT be able to return to it. As a result, these questions will not appear in the review screen.
A manufacturing plant uses Lean process. You plan to outsource a painting operation to a subcontracting vendor. You create a service item named SP-01 to represent the painting service.
You need to create a subcontracting activity for the painting service.
Solution:
1.) Create a purchase agreement for the subcontracting vendor and add SP-01 as the painting service
2.) Create a vendor resource then create a work cell for outsourced painting and add the resource to the work cell
3.) Create a production flow process activity for the painting work cell and add the component to be painted as a picking activity
4.) Create a service term to tie the purchase agreement to the activity Does this solution meet the goal?
MB-320 Exam Question 104
You are the production scheduler at a manufacturing company. You schedule estimated production orders and ensure that capacity is used efficiently.
You have an order that must be scheduled at the resource group level and scheduled backward from the delivery date specified on the production order.
You need to schedule the order.
Which scheduling parameters should you use? To answer, select the appropriate option in the answer area.
NOTE: Each correct selection is worth one point.

You have an order that must be scheduled at the resource group level and scheduled backward from the delivery date specified on the production order.
You need to schedule the order.
Which scheduling parameters should you use? To answer, select the appropriate option in the answer area.
NOTE: Each correct selection is worth one point.

MB-320 Exam Question 105
Note: This question is part of a series of questions that present the same scenario. Each question in the series contains a unique solution that might meet the stated goals. Some question sets might have more than one correct solution, while others might not have a correct solution.
After you answer a question in this section, you will NOT be able to return to it. As a result, these questions will not appear in the review screen.
A company implements Dynamics 365 for Finance and Operations for their Lean manufacturing environment.
There has been an engineering change to a fixed quantity product that is in production. This change will add an additional processing step as the second step. The existing version must be phased out and replaced by the new version.
You need to ensure that the engineering change takes affect at the end of the month.
Solution:
* Add a new version to the existing production flow. Set the expiration date to the end of the month.
* Create an activity for the new process step and add it in the proper sequence.
* Create a Kanban rule that incorporates the new activity. Set the expiration date to the end of the month.
* Edit the existing Kanban rule. Set the expiration date to the end of the month. Specify the new Kanban rule as the replacement rule.
Does the solution meet the goal?
After you answer a question in this section, you will NOT be able to return to it. As a result, these questions will not appear in the review screen.
A company implements Dynamics 365 for Finance and Operations for their Lean manufacturing environment.
There has been an engineering change to a fixed quantity product that is in production. This change will add an additional processing step as the second step. The existing version must be phased out and replaced by the new version.
You need to ensure that the engineering change takes affect at the end of the month.
Solution:
* Add a new version to the existing production flow. Set the expiration date to the end of the month.
* Create an activity for the new process step and add it in the proper sequence.
* Create a Kanban rule that incorporates the new activity. Set the expiration date to the end of the month.
* Edit the existing Kanban rule. Set the expiration date to the end of the month. Specify the new Kanban rule as the replacement rule.
Does the solution meet the goal?