MB-320 Exam Question 11
A company uses warehouse management and manufacturing execution to process their production orders.
You configure the manufacturing execution production order defaults to always consume Bill of materials (BOM) components when an operation step is completed in the job registration terminal. You create a production order. The order is in released status.
You need to process this order all the way through to end status.
Which four actions should you perform in sequence? To answer, check the appropriate actions to the answer area and arrange them in the correct order.

You configure the manufacturing execution production order defaults to always consume Bill of materials (BOM) components when an operation step is completed in the job registration terminal. You create a production order. The order is in released status.
You need to process this order all the way through to end status.
Which four actions should you perform in sequence? To answer, check the appropriate actions to the answer area and arrange them in the correct order.

MB-320 Exam Question 12
A company produces homeopathic lotions for pain relief and uses Dynamics 365 for Finance and Operations.
Several components used in the production of the pain-relieving lotion and oils have special government-mandated reporting requirements.
You need to ensure the company can provide the appropriate reporting and tracking for these components.
Which parameters should you use? To answer, select the appropriate options in the answer area.
NOTE: Each correct selection is worth one point.

Several components used in the production of the pain-relieving lotion and oils have special government-mandated reporting requirements.
You need to ensure the company can provide the appropriate reporting and tracking for these components.
Which parameters should you use? To answer, select the appropriate options in the answer area.
NOTE: Each correct selection is worth one point.

MB-320 Exam Question 13
You are the production scheduler at a manufacturing company. You schedule estimated production orders and ensure that capacity is used efficiently.
You have an order that must be scheduled at the resource group level and scheduled backward from the delivery date specified on the production order.
You need to schedule the order.
Which scheduling parameters should you use? To answer, select the appropriate option in the answer area.
NOTE: Each correct selection is worth one point.

You have an order that must be scheduled at the resource group level and scheduled backward from the delivery date specified on the production order.
You need to schedule the order.
Which scheduling parameters should you use? To answer, select the appropriate option in the answer area.
NOTE: Each correct selection is worth one point.

MB-320 Exam Question 14
You produce 100 total units of finished goods. The amount of material used to produce the goods is the equivalent amount of material needed to produce 105 finished goods. The company must track variances in material compared to the original estimated amount You must only use one picking list journal for each production order. You need to post a picking list that accounts for the material required to produce 105 finished goods. What should you do?
MB-320 Exam Question 15
A manufacturing plant uses Lean manufacturing. Operators process Kanban consumption manually by using a mobile device.
The production team must use automatic empty registration for some of the event Kanbans. Registration must occur when the last job of a Kanban is completed.
You need to update the Kanban rule to meet this requirement.
What Kanban setting should you update?
The production team must use automatic empty registration for some of the event Kanbans. Registration must occur when the last job of a Kanban is completed.
You need to update the Kanban rule to meet this requirement.
What Kanban setting should you update?