NCSE-Core Exam Question 11

ABC Corp currently has 50 VMs currently running in production and is interested in sizing a DR cluster. The RTO is 4 hours and the RPO is 2 hours .
Each VM has 100GB of data, with a 5% daily change rate .for retention the customer wants to keep 2 weeks of snaps on the DR cluster.
What is the minimum amount of storage capacity for the remote cluster to meet the customer's data retention
  • NCSE-Core Exam Question 12

    A customer is asking for a quote for a hybrid cluster to run general purpose VMs and an ERP application containing a 500GB database. The customer has a VSAN ReadyNode quote already and looking for a comparable Nutanix solution. They share the following specifications
    3 hosts
    2 x E5-2640v4 CPU
    512GB RAM
    1 x 480GB SSD
    2 x 8TB HDD
    2 x 1GB NIC
    Which two aspects of the requested configuration should cause concern and need for further discovery? (Choose two.)
  • NCSE-Core Exam Question 13

    For security reason an administrator needs to logically separate management and data traffic on Nutanix cluster.
    Which feature should the administrator select for this configuration?
  • NCSE-Core Exam Question 14

    A prospect that is currently virtualized using Dell servers is willing to provide a Live Optics report to assist with sizing a partial infrastructure refresh with Nutanix.
    Which two items from an approach for sampling accurate sizing data with Live Optics? (Choose one)
  • NCSE-Core Exam Question 15

    A prospective customer is concerned about the suitability and design of using Nutanix for an upcoming Avaya IP Office migration.
    Which type of document should the systems engineer (SE) provide?