1D0-1057-25-D Exam Question 1

Your customer has the following setups on the project plan type that they are using for their projects:
Use Task Planned Dates as Task Assignment Dates = Yes
Automatically Roll Up Task Planned Dates = Yes
Synchronize Task Transaction Dates with Planned Dates = No
With these setups in place, you perform the following actions:
1. Create a new subtask (Sub Task 1) with a start date of 15-Jun-2016 on the project that has as start date of 01-Jul-2016.
2. Create another new subtask (Sub Task 2) after the previous action is saved.
What would the correct behavior of the application be after these actions? (Choose the best answer.)
  • 1D0-1057-25-D Exam Question 2

    Which three file-based data imports are available for use in Oracle Project Portfolio Management Cloud?
  • 1D0-1057-25-D Exam Question 3

    While opening an organization tree on the Manage Organization Trees page, you notice that the hierarchy status is displayed as Inactive. Identify the two reasons for the organization tree to be in Inactive status. (Choose two.)
  • 1D0-1057-25-D Exam Question 4

    In a Project Draft Invoice preview, quantity (hours) and unit price (bill rate) are shown as fields on the invoice. Quantity and unit price are then used to calculate the line total, then the total price of the invoice. After the invoice is transferred or created in Receivables, the invoice detail has a quantity of 1, and a unit price equal to the line total. The detailed Unit Price/Quantity does not come through on the Receivables invoice.
    Identify the correct statement about details in the receivables invoice. (Choose the best answer.)
  • 1D0-1057-25-D Exam Question 5

    You are managing a project based on a Waterfall model. You define a project and a project plan in Oracle Project Management with tasks and subtasks applicable to each of the phases of the project:
    Initiation, Discovery, Design, Build, Test, and Deploy. As a project manager, you want to define deliverables for your project requirements that are elucidated during the Discovery phase of your project. You now want to understand how the inheritance between requirements, tasks, and deliverables works.
    Which two are correct statements in this scenario? (Choose two.)