1Z0-1057-21 Exam Question 16

You are set up as a Follower in Manage Tasks. Which two abilities can you accomplish? (Choose two.)
  • 1Z0-1057-21 Exam Question 17

    Your customer started operations and all projects in January 2015. They implemented Enterprise Project Structure for calculating project labor demand by using the Annual option. When they view the labor demand on 15-Dec-2015, the project hierarchy viewer shows data only for the year 2015. The client expected the demand to be shown for a year, from 15-Dec-2015 to 15-Dec-2016.
    Identify how the project hierarchy viewer displayslabor demand information. (Choose the best answer.)
  • 1Z0-1057-21 Exam Question 18

    You have a small project for a period of five months. Your budget amount for each month is spread evenly and is $1000 per month. The first month actual expense is $800 and there is a commitmentfor $600. Now you generate a forecast at the beginning of the second month. Identify the monthly Estimate-To-Complete (ETC) amount that the application would calculate for the remaining four periods, when the ETC generation method includes commitments. (Choose the best answer.)
  • 1Z0-1057-21 Exam Question 19

    You have been asked to set up one active person, who is not a team member in the project, as a quality manager for each quality task created underprojects. However, when you try to assign the quality manager as Task Manager, you cannot find the person's name in the list of values. What is the reason for this problem?
    (Choose the best answer.)
  • 1Z0-1057-21 Exam Question 20

    When implementing Project Performance Reporting, your customer has the following requirements:
    * Every time a project cost is greater than or equal to a threshold, then the project should be shown as critical.
    * As long as a project cost is less than the threshold, the project should be shown as on-track.
    Which threshold levelrule is ideal for this kind of KPI definition? (Choose the best answer.)