As you go through the first-quarter close for your customer, you notice that the burden amounts calculated do not seem to be right. Based on the calculations, you notice that the amounts calculated are not considering the burden schedule override at a task level, which was done during the second month of the quarter. Identify the reason for this problem. (Choose the best answer.)
1Z0-1057-21 Exam Question 23
You cannot generate invoices for a project expenditure item. After running the Generate Invoices program for abillable expenditure item and active contract, the process completes successfully but without any billing, and does not provide any error logs.
The program's processing summary is as follows:
Billing Event Errors 0
Ineligible Contracts 0
Successfully Billing Events Created 0
Ineligible Contract Lines 0
Billing Transaction Exception Errors 0
Ineligible Bill Plans 0
Billing Transaction Exception Warnings 0
Ineligible Associated Projects 0
Successful Billing Transactions 0
Ineligible Expenditure Items 0
DraftInvoice Exception Errors 0
Ineligible Events 0
Draft Invoice Exception Warnings 0
Successful Draft Invoices 0
What was the invoice method classification set to that caused this behavior? (Choose the best answer.)
The program's processing summary is as follows:
Billing Event Errors 0
Ineligible Contracts 0
Successfully Billing Events Created 0
Ineligible Contract Lines 0
Billing Transaction Exception Errors 0
Ineligible Bill Plans 0
Billing Transaction Exception Warnings 0
Ineligible Associated Projects 0
Successful Billing Transactions 0
Ineligible Expenditure Items 0
DraftInvoice Exception Errors 0
Ineligible Events 0
Draft Invoice Exception Warnings 0
Successful Draft Invoices 0
What was the invoice method classification set to that caused this behavior? (Choose the best answer.)
1Z0-1057-21 Exam Question 24
Your organization has created an Enterprise Project Structure (EPS) and your executives review the overall project labor demand by using the EPS. Identify two correct statementsabout the periodic project labor demand. (Choose two.)
1Z0-1057-21 Exam Question 25
Your organization performs revenue recognition based on the Labor and Non-labor Burden schedule types.
Identify the setup required to enable this kind of revenue recognition. (Choose the best answer.)
Identify the setup required to enable this kind of revenue recognition. (Choose the best answer.)