1Z0-1065-20 Exam Question 46
You created a sourcing two-stage sealed RFQ and invited five suppliers to participate. The Technical stage is completed and the Commercial stage is unlocked.
At this time in the award negotiation section, in the Award Line you are able to see only three supplier's responses as active responses. You are not able to see the other two suppliers' data in the active responses.
Which two reasons are causing this? (Choose two.)
At this time in the award negotiation section, in the Award Line you are able to see only three supplier's responses as active responses. You are not able to see the other two suppliers' data in the active responses.
Which two reasons are causing this? (Choose two.)
1Z0-1065-20 Exam Question 47
In the Enterprise Structures setup, which functional area includes tasks to implement Business Units and Inventory Organizations?
1Z0-1065-20 Exam Question 48
When defining supplier content map sets, which three values should you select that may be converted to values in the procurement business unit? (Choose three.)
1Z0-1065-20 Exam Question 49
Identify three profile options that are used to configure Self Service Procurement. (Choose three.)
1Z0-1065-20 Exam Question 50
To set up Project-Driven Supply Chain (PDSC), you enable the feature in the Manufacturing and Supply Chain Materials Management offering.
What are two additional tasks that you also need to complete? (Choose two.)
What are two additional tasks that you also need to complete? (Choose two.)