1Z0-1075-21 Exam Question 1

A manufacturing plant works for two shifts of 8 hours each. The Manufacturing user wants a work center resource R1 of 4 units to be available during a nonworking time outside the regular shift on a particular day.
Identify the sequence of steps to create a resource exception in the Manage Work Center Resource Calendar page.
  • 1Z0-1075-21 Exam Question 2

    Your customer hasthe following business requirement. There are two work definitions created in the application. One Work Definition for Engine Finished Good and other Work Definition for Pallet Finished Good. The Engine Finished Good item should have Pallet Finished Goodsas one of its component.
    Identify the way to establish the relationship between Pallet and Engine Work Definitions.
  • 1Z0-1075-21 Exam Question 3

    Your customer plans to use Oracle Representational State Transfer (REST) API with Oracle Supply Chain Management Cloud (Oracle SCM Cloud) to support integration requirements.
    Identify four REST resources and thecorresponding HTTP action available with Manufacturing Cloud.
  • 1Z0-1075-21 Exam Question 4

    A Production Supervisor queries a Work Order (WO-1025) from the manage Work Orders page. On the Entering Edit Work Order: WO-1025 page, he finds General Information, Operations and History tab, but not the Reservations tab.
    Identify the two reasons that can cause the Reservations tab not to be displayed.
  • 1Z0-1075-21 Exam Question 5

    Your customer is a light assembly manufacturing company that doesn't require shop floor control. A manufacturing engineer wants to generate a work definition automatically for some items, and wants to eliminate the explicit maintenance of work definitions.
    Which three steps must be completed and verified in the Work Definition area?