1Z0-129 Exam Question 51

You are a P6 administrator. You have received a change request against a configured global dashboard, involving the addition of a portlet. How would you make this change?
  • 1Z0-129 Exam Question 52

    Identify three types of activity codes.
  • 1Z0-129 Exam Question 53

    When can an assignee decline a task if an option is enabled for a step?
  • 1Z0-129 Exam Question 54

    The Project Manager selects the "Update units when costs change on resource assignments" option on Calculations tab in Project Details. The Budgeted Cost is $2,000 and the Budgeted Units is 80 for the resource on an activity. If the User assigns the activity an Actual Cost of $1,000, what is the Actual Units for the resource?
  • 1Z0-129 Exam Question 55

    Identify two benefits of customizing user-interface views.