Which statement is true about the patching features provided in Platinum Services?
Correct Answer: B
Oracle Platinum Services provides patching features for the full software stack, which includes operating systems, virtualization, storage software and firmware, and databases. This service is typically performed up to twice per year, allowing customers to schedule the patching at their convenience. The patching is usually done to keep the software and firmware up-to-date and to fix any known security vulnerabilities. It's important to note that patching services are not done automatically during business hours, customer's involvement and schedule is needed, and the rolling and complete downtime approaches are options to minimize the impact on the system during patching. The correct statement about the patching features provided in Platinum Services is that patching services are available for the full software stack up to twice per year. Oracle Platinum Service covers Exadata storage software and firmware patching, and customers must also perform the database patching. The rolling and complete down time approaches are two options for patching, and patching should be scheduled for times when the system is not being heavily used. Patching is not done automatically during business hours. This is covered in section 4.13 of the Oracle Exadata Database Machine X9M Implementation Essentials Official Text Book and Resources [1]. [1] https://docs.oracle.com/en/engineered-systems/exadata-database-machine/x9m/exad-implementing-database-machine-x9m.pdf Search results: [1] Oracle Exadata Storage Server Patching [1][2]. Oracle Exadata Storage Server patching is performed by a team of Oracle engineers [3][2], and includes the latest Oracle... [2] Patching and Upgrades. Oracle Database Machine provides automated patching and upgrades for the full Exadata software stack, up to twice a year, with... [3] Virtualized Exadata. Oracle Database Machine X9M-2 comes with a choice of two patching approaches to accommodate different customer needs: Rolling... [4] Jan 10, 2017 ... Exadata Patching Process. Oracle Exadata Storage Server patching is performed by a team of Oracle engineers [3][2], and includes the latest...
1Z0-902 Exam Question 27
Which of the below is NOT a precaution that should be adhered to in order to ensure the site is safe and ready for
Correct Answer: C
When preparing a site for an Exadata Database Machine, several precautions ensure both the safety of the installation and the optimal performance of the equipment. These precautions include: Avoiding High-Interference Equipment: Installing near devices like photocopy machines, which can emit electromagnetic interference (EMI), is not a specified precaution for Exadata installations. However, attention should be given to site requirements for temperature, power, and proper grounding connections . In contrast, other site requirements include exclusive grounding for Exadata racks, avoiding direct sunlight exposure, and ensuring grounding resistance is less than 10 ohms for shared grounding to minimize electrical risks.
1Z0-902 Exam Question 28
Which two statements are true for the Oracle Exadata Configuration Assistant (OECA)?
Correct Answer: B,E
B and E are true statements for the Oracle Exadata Configuration Assistant (OECA). OECA facilitates PDU power selection initially and after equipment addition, and it allows for the elastic configuration of the hardware. It does not reconfigure the size of disk groups or recreate grid disks, nor does it allow for a single XT storage server in the configuration. The "Add Equipment" input option does allow for the allocation of RU slots for customer equipment. Reference for this information can be found in the Oracle Exadata Database Machine X9M Implementation Essentials Official Text Book and Resources. Search results: [1] Oracle Exadata Database Machine X8-2 [1][2]: Configuration Assistant Guide ... The Oracle Exadata Configuration Assistant (OECA) is a web-based tool that can ... [2] The Oracle Exadata Configuration Assistant (OECA) is a web-based tool that can be used to ... Add Equipment: This input option allows you to allocate RU slots for ... [3] Oracle Exadata Database Machine X7-2 and X7-2L Installation Guide ... The Oracle Exadata Configuration Assistant (OECA) is a web-based tool that can ... [4] The Oracle Exadata Configuration Assistant (OECA) is a web-based tool that can be used to ... Power Selection [1][2]: This input option allows you to select PDU power initially ... [5] Oracle Exadata Database Machine X7-2 and X7-2L Installation Guide ... The Oracle Exadata Configuration Assistant (OECA) is a web-based tool that can ...
1Z0-902 Exam Question 29
Which are two correct statements for managing virtual deployment using Oracle Exadata Deployment Assistant (OEDA)?
Correct Answer: C,D
1. OEDA deployment steps include calibrate cells, create cell disks, and resecure machine2. 2. OEDA sets up key-based authentication for the root user by using the setuprootssh.sh utility included with OEDA2.
1Z0-902 Exam Question 30
A new Exadata Quarter Rack with 2 Database Servers and 3 HC Storage Servers and 3-phase 15kVA PDUs is being installed in a Data Center. However, the Data Center is only providing enough power for a single cable from each PDU. Which statement is correct?
Correct Answer: A
According to the Oracle Exadata Database Machine X9M-2 Data Sheet1, each PDU has two power input cables that can be connected to separate power sources for redundancy. However, if only one power source is available per PDU, then a single cable can be used to provide sufficient power for normal operation. https://www.oracle.com/a/ocom/docs/engineered-systems/exadata/exadata-x9m-2-ds.pdf