1z0-1075-20 Exam Question 11
Your customer has completed the required setup steps for automatic work definition. Identify the option that shows the navigation steps needed to create an automatic work definition.
1z0-1075-20 Exam Question 12
You are in the process of defining a Standard Operation for visual inspection. You want the completion of this standard operation to be reported in all work orders that reference it.
Identify the setup that will fulfill this requirement.
Identify the setup that will fulfill this requirement.
1z0-1075-20 Exam Question 13
In what three ways can you set the overcompletion tolerance for a subcomponent yield, so the job order can report the excess production completion?
1z0-1075-20 Exam Question 14
A manufacturing cloud user wants to print information available in the work order in PDF.
Identify the three reports that the user can print directly from the work order screen using the Print PDF action.
Identify the three reports that the user can print directly from the work order screen using the Print PDF action.
1z0-1075-20 Exam Question 15
A Production Operator needs to load Work Order Transactions from an external system into Manufacturing Cloud.
Identify the correct sequence of tasks to be performed.
Identify the correct sequence of tasks to be performed.