1Z0-1075-21 Exam Question 1
A plant operates three continuous daily shifts of eight hours each for five days in a week. One unit of the resource R1 within the plant is assigned for two shifts to work area W1. On a particular day in a given week, due to unscheduled maintenance that needed to be performed on the resource R1, it was not available for two hours during each of the assigned shifts.
Determine the available capacity of the resource R1 for thatweek.
Determine the available capacity of the resource R1 for thatweek.
1Z0-1075-21 Exam Question 2
Planning Central has collected manufacturing data for a Work Order WO-2045 (Make Item AS1000), where actual duration of work order is 2 days. Item AS1000 manufacturing lead time is 1.25 days.
A plan is run and the Work Order WO-2045 is rescheduled.
Identify the duration of the rescheduled Work Order WO- 2045.
A plan is run and the Work Order WO-2045 is rescheduled.
Identify the duration of the rescheduled Work Order WO- 2045.
1Z0-1075-21 Exam Question 3
Work order costs are computed based on material and resource transactions reported and the cost method of the product. In a manufacturing plant, the production operator has completed a work order WO-001 ensuring proper materials and resource transactions. The materials are costed and resources are defined with rates.
A cost accountant has created cost accounting distributions. Upon reviewing the accounting distributions of the work order WO-001, resources charged to the work order are missing.
Identify the Concurrent Request that needs to be submitted to transfer resource charges to cost accounting.
A cost accountant has created cost accounting distributions. Upon reviewing the accounting distributions of the work order WO-001, resources charged to the work order are missing.
Identify the Concurrent Request that needs to be submitted to transfer resource charges to cost accounting.
1Z0-1075-21 Exam Question 4
A plantruns 24x7 daily using three continuous shifts of 8 hours each. One unit of an equipment resource R1 is assigned to each of the three shifts. On a specific work order, the resource R1 is required to work for 2 hours.
The resource is set up with an efficiency of 50% and utilization of 100%. R1 is scheduled to start on the given work order at noon.
What time will R1 be scheduled to finish, assuming no calendar exceptions have been set?
The resource is set up with an efficiency of 50% and utilization of 100%. R1 is scheduled to start on the given work order at noon.
What time will R1 be scheduled to finish, assuming no calendar exceptions have been set?
1Z0-1075-21 Exam Question 5
Your Customer has implemented Oracle Cloud Manufacturing and the Manufacturing user is in the process of defining Work Definition and Operations. However, this user is unable to assign an ad hoc item, Grease, to an operation.
Identify the reason.
Identify the reason.