ISO-9001-Lead-Auditor Exam Question 56

You work as an external quality consultant for an organisation, 'A', which provides packaged food to the public. You are asked to lead a team (you as the leader and two other auditors) to audit a supplier, 'B', to ISO
9001 which provides packaging materials to your organisation. It is 4 pm and the audit is close to an end; you are having an internal meeting with the team to decide what will be presented to the auditee during the Closing meeting. The Closing meeting was scheduled at 5 pm.
You, as Audit Team Leader, audited top management. You explain to the audit team that you identified two nonconformities:
a. There is no documented information on Top Management Reviews, as required in clause 9.3 of ISO 9001:
2015.
b. There is no evidence of Top Management Commitment as required in clause 5.1 of ISO 9001:2015. (e.g., not ensuring the availability of resources to operate the QMS, not ensuring the establishment of objectives, no promotion of improvement, no promotion of the process approach).
All agreed to present these two nonconformities. They went to meet the Top Management of 'B' and noticed that the General Manager and three other managers (Production, Human Resources, and Sales) were present in the meeting room.
Considering the seriousness of the two nonconformities to Top Management, as audit team leader, from the following select the best option:
  • ISO-9001-Lead-Auditor Exam Question 57

    Select six of the activities that are specifically required by ISO 17021-1 as part third-party (Certification Body) surveillance audit processes.
  • ISO-9001-Lead-Auditor Exam Question 58

    Which of the following two documents does an auditor need to prepare and complete prior to the on-site audit?
  • ISO-9001-Lead-Auditor Exam Question 59

    Select the words that best complete the sentence:

    ISO-9001-Lead-Auditor Exam Question 60

    An internal auditor of a manufacturer of polystyrene packaging products for the electronics industry raised a nonconformity against section 10.3 of ISO 9001 in Report IA202. The nonconformity (NC 3) stated:
    "The reject rate of the finished product of 9.7% needs improvement as it doesn't meet the stated objective of top management of 5%." As the third-party auditor reviewing the internal audit process, you come across the nonconformity. For corrective action, the Quality Manager conducted an investigation into the reject rates. He reported that the collection baskets for products ejecting from the moulding machines were not large enough. About 6% of products fell onto the wet and dirty factory floor. Management stated that replacing the baskets was too costly and ordered the Maintenance Manager to ensure that the floor was kept clean and dry to prevent rejects. The auditor later checked the factory floor, which was wet and dirty in places.
    From the following nonconformities, select three that the auditor could raise to ISO 9001.