    * Activity A takes one week.
    * Activity B takes three weeks.
    * Activity C takes two weeks.
    * Activity D takes five weeks.
    * Activity A starts at the same time as Activity B.
    * Activity C follows Activity B and Activity A.
    * Activity D follows Activity C.
    How long will it take to complete the project?