CAPM Exam Question 241

Which of the following tools and techniques is used to estimate cost?
  • CAPM Exam Question 242

    Which of the following change requests can bring expected future performance of the project work in line with the project management plan?
  • CAPM Exam Question 243

    The project manager has the following information about the estimated duration for an activity:
    * Most likely [tM] - 15 days
    * Pessimistic [tP] - 20 days
    * Optimistic [tO] - 10 days
    What is the estimated duration of this activity, according to the triangular distribution technique?
  • CAPM Exam Question 244

    Which is the tool or technique that is used to obtain the list of activities from the work packages?
  • CAPM Exam Question 245

    Which of the following events would result in a baseline update?