CAPM Exam Question 396

The project budget is set at $150,000. The project duration is planned to be one year.
At the completion of Week 16 of the project, the following information is collected:
Actual cost = $50,000, Plan cost = $45,000, Earned value = $40,000.
What is the cost performance index?
  • CAPM Exam Question 397

    A given schedule activity is most likely to last four weeks. In a best-case scenario, the schedule activity is estimated to last two weeks. In a worst-case scenario, the schedule activity is estimated to last 12 weeks.
    Given these three estimates, what is the expected duration of the activity?
  • CAPM Exam Question 398

    Which Plan Schedule Management tool or technique may involve choosing strategic options to estimate and schedule the project?
  • CAPM Exam Question 399

    A project manager held a meeting and listed all team members' ideas for improving the product on a white board.
    What data gathering technique did the project manager apply?
  • CAPM Exam Question 400

    Using parametric estimating, if an assigned resource is capable of producing 120 units per hour, how many hours are required to produce 12,000 units?