CAPM Exam Question 396
The project budget is set at $150,000. The project duration is planned to be one year.
At the completion of Week 16 of the project, the following information is collected:
Actual cost = $50,000, Plan cost = $45,000, Earned value = $40,000.
What is the cost performance index?
At the completion of Week 16 of the project, the following information is collected:
Actual cost = $50,000, Plan cost = $45,000, Earned value = $40,000.
What is the cost performance index?
CAPM Exam Question 397
A given schedule activity is most likely to last four weeks. In a best-case scenario, the schedule activity is estimated to last two weeks. In a worst-case scenario, the schedule activity is estimated to last 12 weeks.
Given these three estimates, what is the expected duration of the activity?
Given these three estimates, what is the expected duration of the activity?
CAPM Exam Question 398
Which Plan Schedule Management tool or technique may involve choosing strategic options to estimate and schedule the project?
CAPM Exam Question 399
A project manager held a meeting and listed all team members' ideas for improving the product on a white board.
What data gathering technique did the project manager apply?
What data gathering technique did the project manager apply?
CAPM Exam Question 400
Using parametric estimating, if an assigned resource is capable of producing 120 units per hour, how many hours are required to produce 12,000 units?