CAPM Exam Question 381
Which stakeholder classification model groups stakeholders based on their level of authority and their active involvement in the project?
Correct Answer: A
According to the PMBOKGuide and the Standard for Project Management, specifically within the Identify Stakeholders process, the Power/Influence Grid is the specific classification model that groups stakeholders based on their level of authority (power) and their active involvement (influence) in the project.
As per PMI standards, these grids help the project manager prioritize stakeholders and determine the appropriate engagement strategy. The definitions of the axes in this model are:
Power (Authority): The level of ability a stakeholder has to influence the project ' s outcome or the organization ' s strategic direction.
* Influence (Active Involvement): The stakeholder ' s active involvement in the project and their ability to affect others ' decisions or the project ' s execution.

The other options are incorrect based on the following PMI definitions:
Power/Interest Grid: This model groups stakeholders based on their level of authority (power) and their level of concern or curiosity (interest) regarding the project ' s outcomes.
* Influence/Impact Grid: This model groups stakeholders based on their active involvement (influence) in the project and their ability to effect changes to the project ' s planning or execution (impact).
* Salience Model: This is a more complex model that describes classes of stakeholders based on their assessments of three variables: power (level of authority), urgency (need for immediate attention), and legitimacy (their involvement is appropriate).
As per the PMI Lexicon of Project Management Terms, the use of these grids is a critical component of Stakeholder Analysis, ensuring that the project manager focuses the necessary effort on the stakeholders who can most significantly affect project success.
As per PMI standards, these grids help the project manager prioritize stakeholders and determine the appropriate engagement strategy. The definitions of the axes in this model are:
Power (Authority): The level of ability a stakeholder has to influence the project ' s outcome or the organization ' s strategic direction.
* Influence (Active Involvement): The stakeholder ' s active involvement in the project and their ability to affect others ' decisions or the project ' s execution.

The other options are incorrect based on the following PMI definitions:
Power/Interest Grid: This model groups stakeholders based on their level of authority (power) and their level of concern or curiosity (interest) regarding the project ' s outcomes.
* Influence/Impact Grid: This model groups stakeholders based on their active involvement (influence) in the project and their ability to effect changes to the project ' s planning or execution (impact).
* Salience Model: This is a more complex model that describes classes of stakeholders based on their assessments of three variables: power (level of authority), urgency (need for immediate attention), and legitimacy (their involvement is appropriate).
As per the PMI Lexicon of Project Management Terms, the use of these grids is a critical component of Stakeholder Analysis, ensuring that the project manager focuses the necessary effort on the stakeholders who can most significantly affect project success.
CAPM Exam Question 382
A project manager has just completed several brainstorming sessions and has gathered the data to show commonality and differences in one single place. What technique was followed?
Correct Answer: D
According to the PMBOKGuide, the Affinity Diagram is a key data representation technique used in the Collect Requirements and Manage Quality processes. It is specifically designed to organize a large number of ideas or data points generated during brainstorming into logical groups for review and analysis.
* Organizing Brainstorming Data: After a brainstorming session, teams are often left with a massive, disorganized list of ideas. The affinity diagram allows the project manager to map these ideas based on their " affinities " or relationships.
* Finding Commonality and Differences: By grouping related ideas together, the project manager can see which themes are most common (large groups) and which are unique or outliers (differences). This " single place " view makes complex data sets much easier to digest and prioritize.
* Process Application: It is highly effective when the team needs to move from a divergent thinking phase (generating many ideas) to a convergent thinking phase (organizing and selecting ideas).
Analysis of other options:
* A. Collective decision making: This refers to the process of reaching a conclusion or agreement (such as unanimity, majority, or plurality) rather than a visual technique used to organize and show relationships between data points.
* B. Multicriteria decision analysis: This technique uses a decision matrix to provide a systematic analytical approach for establishing criteria (such as risk levels, uncertainty, and valuation) to evaluate and rank many ideas. It is about scoring ideas, not just showing their commonalities.
* C. Mind mapping: While mind mapping also organizes data visually, it typically radiates from a single central concept. An affinity diagram is better suited for taking a large, existing set of disparate ideas from a brainstorming session and sorting them into categories from the bottom up.
Per PMI standards, the Affinity Diagram is the preferred tool for sorting large amounts of data into categories to reveal patterns and structure.
* Organizing Brainstorming Data: After a brainstorming session, teams are often left with a massive, disorganized list of ideas. The affinity diagram allows the project manager to map these ideas based on their " affinities " or relationships.
* Finding Commonality and Differences: By grouping related ideas together, the project manager can see which themes are most common (large groups) and which are unique or outliers (differences). This " single place " view makes complex data sets much easier to digest and prioritize.
* Process Application: It is highly effective when the team needs to move from a divergent thinking phase (generating many ideas) to a convergent thinking phase (organizing and selecting ideas).
Analysis of other options:
* A. Collective decision making: This refers to the process of reaching a conclusion or agreement (such as unanimity, majority, or plurality) rather than a visual technique used to organize and show relationships between data points.
* B. Multicriteria decision analysis: This technique uses a decision matrix to provide a systematic analytical approach for establishing criteria (such as risk levels, uncertainty, and valuation) to evaluate and rank many ideas. It is about scoring ideas, not just showing their commonalities.
* C. Mind mapping: While mind mapping also organizes data visually, it typically radiates from a single central concept. An affinity diagram is better suited for taking a large, existing set of disparate ideas from a brainstorming session and sorting them into categories from the bottom up.
Per PMI standards, the Affinity Diagram is the preferred tool for sorting large amounts of data into categories to reveal patterns and structure.
CAPM Exam Question 383
Which action is included in the Control Costs process?
Correct Answer: D
According to the PMBOK Guide, specifically within the Project Cost Management knowledge area, the Control Costs process is the process of monitoring the status of the project to update the project costs and managing changes to the cost baseline.
* Monitor and Isolate Variances (Option D): This is a core function of the Control Costs process. It involves comparing the actual money spent (Actual Cost) against the planned expenditure (Planned Value) and the physical work performed (Earned Value). By doing so, the project manager can determine the Cost Variance (CV) and the Cost Performance Index (CPI) to understand if the project is over or under budget and why.
* Identify how costs will be planned (Option A): This describes the Plan Cost Management process. This is the initial planning stage where the " rules " for cost management are established.
* Determine policies and objectives (Option B): This is more closely related to Plan Quality Management or general Stakeholder Management, where the project ' s overarching policies are aligned with stakeholder needs.
* Develop an approximation of resources (Option C): This is the definition of the Estimate Costs process, which occurs before the budget is finalized and before control activities begin.
In the PMI framework, the Control Costs process ensures that any changes to the cost baseline are managed through the Perform Integrated Change Control process, ensuring that the project remains financially viable.
* Monitor and Isolate Variances (Option D): This is a core function of the Control Costs process. It involves comparing the actual money spent (Actual Cost) against the planned expenditure (Planned Value) and the physical work performed (Earned Value). By doing so, the project manager can determine the Cost Variance (CV) and the Cost Performance Index (CPI) to understand if the project is over or under budget and why.
* Identify how costs will be planned (Option A): This describes the Plan Cost Management process. This is the initial planning stage where the " rules " for cost management are established.
* Determine policies and objectives (Option B): This is more closely related to Plan Quality Management or general Stakeholder Management, where the project ' s overarching policies are aligned with stakeholder needs.
* Develop an approximation of resources (Option C): This is the definition of the Estimate Costs process, which occurs before the budget is finalized and before control activities begin.
In the PMI framework, the Control Costs process ensures that any changes to the cost baseline are managed through the Perform Integrated Change Control process, ensuring that the project remains financially viable.
CAPM Exam Question 384
When a backward pass is calculated from a schedule constraint that is later than the early finish date that has been calculated during a forward pass calculation, this causes which type of total float?
Correct Answer: C
According to the PMBOKGuide and the Standard for Project Management, specifically within the Develop Schedule process using the Critical Path Method (CPM), the relationship between the forward pass and the backward pass determines the amount of Total Float.
As per PMI standards, Total Float is the amount of time that a schedule activity can be delayed or extended from its early start date without delaying the project finish date or violating a schedule constraint. The calculation for Total Float is:
$$\text{Total Float} = \text{Late Finish (LF)} - \text{Early Finish (EF)}$$ or
$$\text{Total Float} = \text{Late Start (LS)} - \text{Early Start (ES)}$$ In the scenario described:
* Forward Pass: Calculates the Early Finish (EF) date.
* Backward Pass: Starts from a Schedule Constraint (the required completion date).
* The Condition: The constraint (LF) is later (further in the future) than the calculated EF.
Because the Late Finish is greater than the Early Finish, the result of the subtraction is a Positive value. This indicates that the project or activity has " extra " time or a buffer before it would impact the mandatory constraint.
The other options are incorrect based on the following PMI scheduling logic:
* Negative: This occurs when a schedule constraint is earlier than the calculated early finish date ($LF < EF$), indicating the project is already behind the required deadline.
* Zero: This occurs when the late finish is equal to the early finish ($LF = EF$), which is typical for activities on the Critical Path.
* Free: This is the amount of time an activity can be delayed without delaying the Early Start of any successor activity. It is a relationship between activities, whereas the question describes a relationship between a pass calculation and a project-level constraint.
As per the PMI Lexicon of Project Management Terms, understanding positive float is essential for resource leveling, as it identifies which activities have flexibility to be shifted without jeopardizing the final deadline.
As per PMI standards, Total Float is the amount of time that a schedule activity can be delayed or extended from its early start date without delaying the project finish date or violating a schedule constraint. The calculation for Total Float is:
$$\text{Total Float} = \text{Late Finish (LF)} - \text{Early Finish (EF)}$$ or
$$\text{Total Float} = \text{Late Start (LS)} - \text{Early Start (ES)}$$ In the scenario described:
* Forward Pass: Calculates the Early Finish (EF) date.
* Backward Pass: Starts from a Schedule Constraint (the required completion date).
* The Condition: The constraint (LF) is later (further in the future) than the calculated EF.
Because the Late Finish is greater than the Early Finish, the result of the subtraction is a Positive value. This indicates that the project or activity has " extra " time or a buffer before it would impact the mandatory constraint.
The other options are incorrect based on the following PMI scheduling logic:
* Negative: This occurs when a schedule constraint is earlier than the calculated early finish date ($LF < EF$), indicating the project is already behind the required deadline.
* Zero: This occurs when the late finish is equal to the early finish ($LF = EF$), which is typical for activities on the Critical Path.
* Free: This is the amount of time an activity can be delayed without delaying the Early Start of any successor activity. It is a relationship between activities, whereas the question describes a relationship between a pass calculation and a project-level constraint.
As per the PMI Lexicon of Project Management Terms, understanding positive float is essential for resource leveling, as it identifies which activities have flexibility to be shifted without jeopardizing the final deadline.
CAPM Exam Question 385
What is one of the objectives of Project Risk Management?
Correct Answer: C
According to the PMBOKGuide, specifically within the Project Risk Management knowledge area, the fundamental objective of project risk management is to increase the probability and/or impact of positive risks (opportunities) and to decrease the probability and/or impact of negative risks (threats).
* Opportunities vs. Threats: In PMI methodology, " risk " is an uncertain event or condition that, if it occurs, has a positive or negative effect on one or more project objectives. Therefore, risk management is not just about avoiding bad things; it is equally about capturing good things.
* Managing Opportunities: Strategies for positive risks include Escalate, Exploit, Share, Enhance, and Accept. By " Enhancing " a risk, the project manager actively works to increase the chance of the opportunity occurring or the magnitude of the benefit it provides.
* Optimizing Project Success: By focusing on both sides of the risk spectrum, the project manager maximizes the likelihood of project success. For example, finishing a project early (a positive risk) is just as much a subject of risk management as a potential delay (a negative risk).
* Continuous Process: Risk management is iterative. Throughout the project life cycle, new opportunities may emerge that require the team to shift resources or change tactics to " Increase the impact " of those positive events.
Comparison with other options:
* A. Decrease the probability and impact of an event...: This statement is incomplete. While we want to decrease the impact of negative events (threats), we want to increase the impact of positive events.
* B. Distinguish between a project risk and a project issue...: While distinguishing between the two is an important administrative task (risks are uncertain future events, issues are current certainties), it is a step in the process, not a primary objective of the entire Risk Management knowledge area.
* D. Removal of project risk: It is virtually impossible to " remove " all project risk. Even if specific risks are avoided, the act of doing a project inherently involves uncertainty. The goal is to manage and optimize risk, not necessarily eliminate it entirely.
* Opportunities vs. Threats: In PMI methodology, " risk " is an uncertain event or condition that, if it occurs, has a positive or negative effect on one or more project objectives. Therefore, risk management is not just about avoiding bad things; it is equally about capturing good things.
* Managing Opportunities: Strategies for positive risks include Escalate, Exploit, Share, Enhance, and Accept. By " Enhancing " a risk, the project manager actively works to increase the chance of the opportunity occurring or the magnitude of the benefit it provides.
* Optimizing Project Success: By focusing on both sides of the risk spectrum, the project manager maximizes the likelihood of project success. For example, finishing a project early (a positive risk) is just as much a subject of risk management as a potential delay (a negative risk).
* Continuous Process: Risk management is iterative. Throughout the project life cycle, new opportunities may emerge that require the team to shift resources or change tactics to " Increase the impact " of those positive events.
Comparison with other options:
* A. Decrease the probability and impact of an event...: This statement is incomplete. While we want to decrease the impact of negative events (threats), we want to increase the impact of positive events.
* B. Distinguish between a project risk and a project issue...: While distinguishing between the two is an important administrative task (risks are uncertain future events, issues are current certainties), it is a step in the process, not a primary objective of the entire Risk Management knowledge area.
* D. Removal of project risk: It is virtually impossible to " remove " all project risk. Even if specific risks are avoided, the act of doing a project inherently involves uncertainty. The goal is to manage and optimize risk, not necessarily eliminate it entirely.
- Other Version
- 2833PMI.CAPM.v2026-09-05.q632
- 4834PMI.CAPM.v2026-07-17.q643
- 5497PMI.CAPM.v2023-02-14.q281
- 12147PMI.CAPM.v2022-05-24.q570
- 59PMI.Pass4guide.CAPM.v2022-05-12.by.shirley.570q.pdf
- 14992PMI.CAPM.v2022-01-02.q768
- 89PMI.Exams4sures.CAPM.v2021-08-25.by.odelette.722q.pdf
- Latest Upload
- 195Oracle.1Z0-1110-26.v2026-10-17.q71
- 242CloudSecurityAlliance.CCSK.v2026-10-17.q153
- 238Salesforce.Platform-App-Builder.v2026-10-17.q161
- 160Salesforce.AP-204.v2026-10-17.q40
- 235Microsoft.AI-103.v2026-10-16.q46
- 221InsuranceLicensing.NY-Independent-General-Adjuster.v2026-10-15.q45
- 288Anthropic.CCAR-F.v2026-10-15.q76
- 259Salesforce.Marketing-Cloud-Consultant.v2026-10-15.q68
- 789PMI.CAPM.v2026-10-15.q575
- 219ServiceNow.CIS-DF.v2026-10-15.q61